Strengthening Risk Information for Disaster Resilience in Bhutan

Résumé*

The proposed project consists of (i) the development of a Multi-Hazard Risk Decision Support System based on a national level multi-hazard risk assessment and its implementation through capacity building, training and advocacy; (ii) strengthening hydromet and climate services delivery through the development and adoption of a National Hydrology and Meteorology Policy and support for the delivery of weather, water and climate services at local levels...

* Le résumé de projet étant tiré du document d'évaluation de projet (PAD), du rapport d'évaluation (SAR) ou du document du programme (PGD), il peut ne pas refléter exactement la teneur du projet en son état actuel.

Voir plus

Objectif de développement

To enhance Bhutan’s capacity for risk-informed decision making and development planning in targeted sectors.

Clé Détails

Projet Détails

  • P175081

  • Active

  • Naho Shibuya , Mohammad Rafiqul Islam

  • The Kingdom of Bhutan

  • Bhoutan

  • 17 février 2021

  • (à la date de présentation au Conseil)

    26 novembre 2021

  • 11 décembre 2021

  • USD 3.51 millions

  • National Center for Hydrology and Meteorology,Ministry of Infrastructure and Transport,Department of Agriculture,Bhutan Construction and Transport Authority,Department of Local Governance and Disaster Management

  • Asie du Sud

  • 2022

  • USD 3.51 millions

  • N/A

  • 29 mai 2024

  • 30 juin 2026

  • Yes

  • BANK APPROVED

  • Notes

Finances

Plan De Financement (Millions De Dollars)

Pas de données disponibles.
Org. De Financement Engagements
Global Facility for Disaster Reduction and Recovery 1.21
Climate Investment Funds 2.30

Financement total du projet (USD millions)

Type de produit/service BIRD/IDA
Engagement BIRD N/D
Engagement IDA N/D
Engagement BIRD + IDA N/D
Instrument de prêt
Élément don 3.51
Coût total du projet** 3.51

État récapitulatif du financement de la Banque (USD millions) au 28 février 2025

Télécharger:
Pas de données disponibles.
Org. De Financement Date D'approbation Date De Cloture Montant En Principal Décaissé Remboursements Intérêts, Charges Et Commissions Financières

Activité financière détaillée au 28 février 2025

Télécharger:
Pas de données disponibles.
Période Org. De Financement Type De Transaction Montant (USD)

Footnotes

Ratings

EXÉCUTION DU PROJET

Name Review Date
Progress towards achievement of PDO Satisfactory 2024-08-13
Overall Implementation Progress (IP) Satisfactory 2024-08-13

FIN D’EXÉCUTION DU PROJET

Pas de données disponibles.

NOTATION DE L’ÉVALUATION INDÉPENDANTE

Pas de données disponibles.

Cadre de résultats

INDICATEURS DES OBJECTIFS DE DÉVELOPPEMENT DU PROJET

INDICATEURNIVEAU DE RÉFÉRENCE EN COURS OBJECTIF
  • Number of critical sectors having risk information generated through the multi-hazard risk decision support system (MHRDSS)Valeur0.001.003.00
    Date31 mars 202123 juin 202330 juin 2025
    Observation
  • Improved capacity of NCHM in providing medium-range weather forecasts and products for agromet servicesValeurNCHM provides 3-day weather forecasts and seasonalNCHM provides 3-day weather forecasts and seasonalNCHM provides medium-range (10 days) weather forec
    Date31 juillet 202123 juin 202331 décembre 2022
    Observation

INDICATEURS DE RÉSULTATS INTERMÉDIAIRES

INDICATEURNIVEAU DE RÉFÉRENCE EN COURS OBJECTIF
  • Number of public and private users trained on the use of MHRDSSValeur0.0041.00200.00
    Date31 mars 202123 juin 202330 juin 2025
    Observation
  • Policies and strategic plans for promoting disaster and climate resilience enhancedValeur0.007.004.00
    Date31 mars 202123 juin 202330 juin 2025
    Observation
  • Gewogs (villages) in which the ADSS is implemented for disseminating agromet advisoriesValeur0.000.0011.00
    Date31 mars 202123 juin 202330 juin 2025
    Observation
  • Farmers trained on climate risks and the use of agromet advisoriesValeur0.000.00440.00
    Date31 mars 202123 juin 202330 juin 2025
    Observation
  • Private sector construction professionals trained on resilient infrastructure planning and developmentValeur0.000.00500.00
    Date31 mars 202123 juin 202330 juin 2025
    Observation
  • MHRDSS developed based on multi-hazard risk assessmentValeurNoNoYes
    Date31 juillet 202123 juin 202330 juin 2025
    Observation
  • Number of NCHM officials trained on medium-range weather forecastsValeur0.000.005.00
    Date31 juillet 202123 juin 202330 juin 2025
    Observation
  • Percentage of women trainedValeur0.0022.0040.00
    Date31 mars 202123 juin 202330 juin 2025
    Observation
  • Percentage of women trainedValeur0.000.0040.00
    Date31 mars 202123 juin 202330 juin 2025
    Observation
  • Percentage of women trainedValeur0.000.0030.00
    Date31 mars 202123 juin 202330 juin 2025
    Observation
  • Roads in hazard-prone areas inspected, and landslides recordedValeur0.002258.0020800.00
    Date31 juillet 202123 juin 202330 juin 2025
    Observation