Skip to Main Navigation

Gazetted Forests Management Project

Résumé*

The development objective of the Gazetted Forests Management Project for Benin is to improve the integrated management of targeted Gazetted Forests, to increase access of the main consumption cities to fuelwood produced sustainably, and to strengthen selected non-timber forest product value chains for forest-dependent communities.It has four components. First component, Support to Forests Governance aims to enhance the capacity of the Forestry Administration...

* Le résumé de projet étant tiré du document d'évaluation de projet (PAD), du rapport d'évaluation (SAR) ou du document du programme (PGD), il peut ne pas refléter exactement la teneur du projet en son état actuel.

Voir plus

Objectif de développement

To improve the integrated management of targeted Gazetted Forests, to increase access of the main consumption cities to fuelwood produced sustainably, and to strengthen selected non-timber forest product value chains for forest-dependent communities

Clé Détails

Projet Détails

  • P167678

  • Active

  • Jean-Dominique Bescond , Manuela Ravina da Silva

  • Ministry of Economy of the Republic of Benin

  • Bénin

  • 25 juin 2018

  • (à la date de présentation au Conseil)

    30 mai 2019

  • 1 octobre 2019

  • USD 75.00 millions

  • Ministry of Environment and Sustainable Development

  • Western and Central Africa

  • 2019

  • USD 60.10 millions

  • B

  • 20 mars 2024

  • 30 novembre 2026

  • TBD

  • BANK APPROVED

  • Notes

Finances

Plan De Financement (Millions De Dollars)

Pas de données disponibles.
Org. De Financement Engagements
IDA Grant 60.10

Financement total du projet (USD millions)

Type de produit/service BIRD/IDA
Engagement BIRD N/D
Engagement IDA 60.10
Engagement BIRD + IDA 60.10
Instrument de prêt
Élément don N/D
Coût total du projet** 75.00

État récapitulatif du financement de la Banque (USD millions) au 28 février 2025

Télécharger:
Pas de données disponibles.
Org. De Financement Date D'approbation Date De Cloture Montant En Principal Décaissé Remboursements Intérêts, Charges Et Commissions Financières

Activité financière détaillée au 28 février 2025

Télécharger:
Pas de données disponibles.
Période Org. De Financement Type De Transaction Montant (USD)

Footnotes

Ratings

EXÉCUTION DU PROJET

Name Review Date
Overall Implementation Progress (IP) Satisfactory 2024-11-12
Procurement Satisfactory 2024-11-12
Project Management Moderately Satisfactory 2024-11-12
Monitoring and Evaluation Moderately Satisfactory 2024-11-12
Progress towards achievement of PDO Satisfactory 2024-11-12
Financial Management Satisfactory 2024-11-12

FIN D’EXÉCUTION DU PROJET

Pas de données disponibles.

NOTATION DE L’ÉVALUATION INDÉPENDANTE

Pas de données disponibles.

Cadre de résultats

INDICATEURS DES OBJECTIFS DE DÉVELOPPEMENT DU PROJET

INDICATEURNIVEAU DE RÉFÉRENCE EN COURS OBJECTIF
  • PDO Indicator 1: Gazetted Forest areas under sustainable management based on defined criteriaValeur8909.0017716.00917951.00
    Date31 mai 20192 octobre 202330 novembre 2026
    Observation
  • PDO Indicator 2: Net greenhouse gas emissionsValeur0.003119976.0012600000.00
    Date31 mai 20192 octobre 202330 novembre 2026
    Observation
  • PDO Indicator 3: Standing volume of wood energy plantationsValeur10800.00320000.001810800.00
    Date31 mai 20192 octobre 202330 novembre 2026
    Observation
  • PDO Indicator 4: Communities adjacent to targeted GFs with increased access to income sources through NTFP value chainsValeur0.000.001000.00
    Date31 mai 20192 octobre 202330 novembre 2026
    Observation
  • PDO Indicator 5: Satisfaction of beneficiaries (level of engagement, by gender and age)Valeur0.0093.0070.00
    Date31 mai 20192 octobre 202330 novembre 2026
    Observation

INDICATEURS DE RÉSULTATS INTERMÉDIAIRES

INDICATEURNIVEAU DE RÉFÉRENCE EN COURS OBJECTIF
  • Intermediate Indicator 1: Forest area brought under management plansValeur0.000.00917951.00
    Date31 mai 20192 octobre 202330 novembre 2026
    Observation
  • Intermediate Indicator 5: Transhumance corridors created by the projectValeur1.000.0011.00
    Date31 mai 20192 octobre 202330 novembre 2026
    Observation
  • Intermediate Indicator 10: Honey producers organized and producing honey for national and regional saleValeur0.000.00200.00
    Date31 mai 20192 octobre 202330 novembre 2026
    Observation
  • Shea trees established and managed in and around targeted GFs in the northValeur0.000.00500.00
    Date31 mai 20192 octobre 202330 novembre 2026
    Observation
  • Intermediate Indicator 6: Producers adopting improved carbonization techniquesValeur0.000.00300.00
    Date31 mai 20192 octobre 202330 novembre 2026
    Observation
  • Intermediate Indicator 2: Areas of GF patrolled by the forest rangersValeur883.002010.007983.00
    Date31 mai 20192 octobre 202330 novembre 2026
    Observation
  • of which womenValeur0.000.00200.00
    Date12 mars 20192 octobre 202330 novembre 2026
    Observation
  • Women shea nut collectors organized and producing energy-efficient shea butter for national and regional saleValeur0.000.00200.00
    Date31 mai 20192 octobre 202330 novembre 2026
    Observation
  • Intermediate Indicator 7: Plantations of wood energy established and managed (disaggregated by GF)Valeur90.0018732.0015090.00
    Date31 mai 20192 octobre 202330 novembre 2026
    Observation
  • Intermediate Indicator 3: Improved organizational arrangements for GF submitted to the Government for adoptionValeurNoNoYes
    Date31 mai 20192 octobre 202330 novembre 2026
    Observation
  • DanValeur35.00835.001235.00
    Date31 mai 20194 octobre 202230 novembre 2026
    Observation
  • Intermediate Indicator 4: Financial instrument selected to finance recurrent costs of GF management in the long runValeurNoNoYes
    Date31 mai 20192 octobre 202330 novembre 2026
    Observation
  • KetouValeur45.003114.003045.00
    Date31 mai 20194 octobre 202230 novembre 2026
    Observation
  • LogozoheValeur0.001162.001300.00
    Date31 mai 20194 octobre 202230 novembre 2026
    Observation
  • Oueme-BoukouValeur10.002760.003010.00
    Date31 mai 20194 octobre 202230 novembre 2026
    Observation
  • Tchaourou-Toui-KiliboValeur0.002688.003500.00
    Date31 mai 20194 octobre 202230 novembre 2026
    Observation
  • AgouaValeur0.003156.003000.00
    Date31 mai 20194 octobre 202230 novembre 2026
    Observation
  • Intermediate Indicator 8: Surface areas granted to farmers to apply the taungya systemValeur0.002500.005000.00
    Date31 mai 20192 octobre 202330 novembre 2026
    Observation
  • of which womenValeur0.0055.002500.00
    Date12 mars 20192 octobre 202329 mai 2026
    Observation
  • Intermediate Indicator 9: Plantations of timber established and managed (disaggregated by GF)Valeur805.005815.007805.00
    Date31 mai 20192 octobre 202330 novembre 2026
    Observation
  • DogoValeur805.003418.005805.00
    Date31 mai 20193 avril 202330 novembre 2026
    Observation
  • ToffoValeur0.00833.002000.00
    Date31 mai 20193 avril 202330 novembre 2026
    Observation
  • Farmers adopting improved agricultural technologyValeur0.002500.002000.00
    Date31 mai 20192 octobre 202330 novembre 2026
    Observation
  • Surface areas brought under enhanced biodiversity conservationValeur0.000.00367000.00
    Date31 mai 20192 octobre 202330 novembre 2026
    Observation