The objective of the Governance to Enable Service Delivery Project for Malawi is to strengthen Local Authorities’ institutional performance, responsiveness to citizens and management of resources for service delivery. The Project has four components. 1. Performance-Based Financing for Service Delivery component will substantially enhance predictable development financing for LAs in a manner that incentivizes sustained improvements in efficiency, equity...

* Le résumé de projet étant tiré du document d'évaluation de projet (PAD), du rapport d'évaluation (SAR) ou du document du programme (PGD), il peut ne pas refléter exactement la teneur du projet en son état actuel.

Voir plus

Objectif de développement

The objective of the Project is to: (i) strengthen Local Authorities’ institutional performance, responsiveness to citizens and management of resources for service delivery; and (ii) in case of an Eligible Crisis or Emergency, respond promptly and effectively to it.

Clé Détails

Projet Détails

  • P164961

  • Active

  • Michael Roscitt

  • Republic of Malawi

  • Malawi

  • 15 août 2018

  • (à la date de présentation au Conseil)

    30 avril 2020

  • 16 décembre 2020

  • USD 100.00 millions

  • National Local Government Finance Committee

  • Eastern and Southern Africa

  • 2020

  • USD 100.00 millions

  • B

  • N/A

  • 30 juin 2026

  • No

  • BANK APPROVED

  • 18 avril 2024

  • Notes

Finances

Plan De Financement (Millions De Dollars)

Pas de données disponibles.
Org. De Financement Engagements
IDA Grant 100.00

Financement total du projet (USD millions)

Type de produit/service BIRD/IDA
Engagement BIRD N/D
Engagement IDA 100.00
Engagement BIRD + IDA 100.00
Instrument de prêt
Élément don N/D
Coût total du projet** 100.00

État récapitulatif du financement de la Banque (USD millions) au 31 mars 2025

Télécharger:
Pas de données disponibles.
Org. De Financement Date D'approbation Date De Cloture Montant En Principal Décaissé Remboursements Intérêts, Charges Et Commissions Financières

Activité financière détaillée au 31 mars 2025

Télécharger:
Pas de données disponibles.
Période Org. De Financement Type De Transaction Montant (USD)

Footnotes

Ratings

EXÉCUTION DU PROJET

Name Review Date
Progress towards achievement of PDO Satisfactory 2025-03-14
Financial Management Satisfactory 2025-03-14
Overall Implementation Progress (IP) Moderately Satisfactory 2025-03-14
Procurement Moderately Satisfactory 2025-03-14
Monitoring and Evaluation Moderately Satisfactory 2025-03-14
Overall Safeguards Rating Moderately Satisfactory 2025-03-14
Project Management Satisfactory 2025-03-14

FIN D’EXÉCUTION DU PROJET

Pas de données disponibles.

NOTATION DE L’ÉVALUATION INDÉPENDANTE

Pas de données disponibles.

Cadre de résultats

INDICATEURS DES OBJECTIFS DE DÉVELOPPEMENT DU PROJET

INDICATEURNIVEAU DE RÉFÉRENCE EN COURS OBJECTIF
  • Local Authorities that are eligible for the Performance Based GrantValeur0.0028.0026.00
    Date30 septembre 20191 mars 202430 septembre 2025
    Observation
  • Local Authorities that increase their performance assessment score by at least 5 pointsValeur0.0017.0015.00
    Date30 septembre 20191 mars 202430 septembre 2025
    Observation
  • Local Authorities that complete 80% of the capital investment projects in their Annual Investment PlansValeur10.0018.0026.00
    Date30 septembre 201915 décembre 202330 septembre 2025
    Observation
  • Increase in citizen satisfaction (disaggregated by sex) with preparation and implementation of Annual Investment Plans based on periodic beneficiary feedback surveyValeur0.0013.0025.00
    Date30 septembre 201915 décembre 202330 septembre 2025
    Observation

INDICATEURS DE RÉSULTATS INTERMÉDIAIRES

INDICATEURNIVEAU DE RÉFÉRENCE EN COURS OBJECTIF
  • Annual local authority performance assessment conducted on time with quality assurance and results published and used to determine District allocation of the Performance-Based GrantValeurNoYesYes
    Date30 septembre 201929 mars 202430 septembre 2025
    Observation
  • Progressive improvement in transparency, policy coherence and accountability in intergovernmental fiscal transfer System (IGFTs)ValeurNo fiscal decentralization strategy; IGFTS not traDraft fiscal decentralization strategy producedNLGFC publishes annual report on the IGFTs, progre
    Date30 septembre 201929 mars 202430 septembre 2025
    Observation
  • Vacancy rate for core functions across Local AuthoritiesValeur56.0044.0020.00
    Date30 septembre 201929 mars 202430 septembre 2025
    Observation
  • District Development Fund (DDF) released to Local Authorities on time and in full amount allocated in approved budgetValeurNoYesYes
    Date30 septembre 201931 mars 202330 septembre 2025
    Observation
  • Local Authority financial statements audited by National Audit Office by December 31 of each yearValeur0.0028.0028.00
    Date30 septembre 201929 mars 202430 septembre 2025
    Observation
  • Local Authorities that submit quarterly physical progress reports for Annual Investment Plan (AIP) projectsValeur0.0014.0015.00
    Date30 septembre 201915 décembre 202330 septembre 2025
    Observation
  • Targeted Local Government Performance Improvement Plans for the bottom 5 scoring Local Authorities developed and implementedValeur0.005.005.00
    Date30 septembre 201929 mars 202430 septembre 2025
    Observation
  • Local Authorities that improve their performance on Financial Management and AccountingValeur0.0016.0018.00
    Date30 septembre 201929 mars 202430 septembre 2025
    Observation
  • Local Authorities that each year produce and act on at least 2 semi-annual internal audit reportsValeur0.0018.0026.00
    Date30 septembre 201929 mars 202430 septembre 2025
    Observation
  • Gender sensitive standards for selection of Annual Investment Plan projects in placeValeurN/AGender-sensitive standards draftedNLGFC Annual Report reports on use and impact of g
    Date30 septembre 201929 mars 202430 septembre 2025
    Observation
  • Improved citizen engagement on Annual Investment Plans as measured by the Performance Measures relating to citizen engagement and access to informationValeurN/A2420
    Date30 septembre 201929 mars 202430 septembre 2025
    Observation