Southern Africa Trade and Connectivity Project

Résumé*

The project development objective of the Malawi and Mozambique - Southern Africa Trade and Connectivity Project is to support Malawi and Mozambique in increasing regional trade coordination, reducing trade costs and time, developing regional value chains, and improving access to infrastructure. The project adopts the RICAS (FY18-23) infrastructure “plus” approach. The project’s components directly respond to the strategic pillars of the Regional Integration...

* Le résumé de projet étant tiré du document d'évaluation de projet (PAD), du rapport d'évaluation (SAR) ou du document du programme (PGD), il peut ne pas refléter exactement la teneur du projet en son état actuel.

Voir plus

Objectif de développement

The project development objective is to support Malawi and Mozambique in increasing regional trade coordination, reducing trade costs and time, and developing regional value chains.

Clé Détails

Projet Détails

  • P164847

  • Active

  • Ankur Huria , Laurent Corthay, Monica Moldovan

  • Republic of Mozambique,Republic of Malawi

  • Afrique australe

  • 9 décembre 2020

  • (à la date de présentation au Conseil)

    27 avril 2021

  • 24 septembre 2021

  • USD 380.00 millions

  • Ministry of Transport and Logistics, Republic of Mozambique,Roads Authority, Republic of Malawi,Ministry of Transport and Public Works, Republic of Malawi,Fundo de Estradas, Republic of Mozambique

  • Eastern and Southern Africa

  • 2021

  • USD 380.00 millions

  • A

  • 21 février 2024

  • 30 juin 2027

  • Yes

  • BANK APPROVED

  • Notes

Finances

Plan De Financement (Millions De Dollars)

Pas de données disponibles.
Org. De Financement Engagements
IDA Credit 75.00
IDA Grant 305.00

Financement total du projet (USD millions)

Type de produit/service BIRD/IDA
Engagement BIRD N/D
Engagement IDA 380.00
Engagement BIRD + IDA 380.00
Instrument de prêt
Élément don N/D
Coût total du projet** 380.00

État récapitulatif du financement de la Banque (USD millions) au 31 mars 2025

Télécharger:
Pas de données disponibles.
Org. De Financement Date D'approbation Date De Cloture Montant En Principal Décaissé Remboursements Intérêts, Charges Et Commissions Financières

Activité financière détaillée au 31 mars 2025

Télécharger:
Pas de données disponibles.
Période Org. De Financement Type De Transaction Montant (USD)

Footnotes

Ratings

EXÉCUTION DU PROJET

Name Review Date
Overall Safeguards Rating Satisfactory 2024-09-04
Progress towards achievement of PDO Moderately Unsatisfactory 2024-09-04
Procurement Moderately Satisfactory 2024-09-04
Project Management Moderately Unsatisfactory 2024-09-04
Financial Management Satisfactory 2024-09-04
Monitoring and Evaluation Satisfactory 2024-09-04
Overall Implementation Progress (IP) Moderately Unsatisfactory 2024-09-04

FIN D’EXÉCUTION DU PROJET

Pas de données disponibles.

NOTATION DE L’ÉVALUATION INDÉPENDANTE

Pas de données disponibles.

Cadre de résultats

INDICATEURS DES OBJECTIFS DE DÉVELOPPEMENT DU PROJET

INDICATEURNIVEAU DE RÉFÉRENCE EN COURS OBJECTIF
  • Increase in sales of value chain actors participating in the supported value chainsValeur0.000.0020.00
    Date1 décembre 20208 septembre 202230 juin 2027
    Observation
  • Decrease in logistics cost of containerized imports/exports $ per ton at destinationValeur0.000.0018.00
    Date1 décembre 20208 septembre 202230 juin 2027
    Observation
  • Share of population with enhanced access to infrastructureValeur0.000.00100.00
    Date1 décembre 20208 septembre 202230 juin 2027
    Observation
  • Percentage of key corridor performance indicators with operational improvement made as measured by the corridor performance monitoring mechanism.Valeur0.000.0030.00
    Date1 décembre 20208 septembre 202230 juin 2027
    Observation
  • Number of women value chain actors supported by value chain development activitiesValeur0.000.001000.00
    Date
    Observation
  • Decrease in logistics cost of containerized imports $ per ton at destination (Nacala to Blantyre, Road).Valeur0.000.0020.00
    Date
    Observation
  • Value of private sector investments catalyzed (through matching grants) in Malawi and MozambiqueValeur0.000.0015000000.00
    Date1 décembre 20208 septembre 202230 juin 2027
    Observation
  • Decrease in logistics cost of containerized imports $ per ton at destination (Nacala to Blantyre, Rail)Valeur0.000.0010.00
    Date
    Observation
  • Decrease in logistics cost of containerized imports $ per ton at destination (Beira to Blantyre, Road)Valeur0.000.0020.00
    Date
    Observation
  • Decrease in logistics cost of containerized exports in $ per ton to port (Blantyre to Beira, road).Valeur0.000.0020.00
    Date
    Observation
  • Decrease in logistics cost of containerized exports in $ per ton to port (Blantyre to Nacala, rail).Valeur0.000.0010.00
    Date
    Observation
  • Decrease in average time to clear a border crossingValeur0.000.0020.00
    Date1 décembre 20218 septembre 202230 juin 2027
    Observation
  • Decrease in average time to clear Muloza-Milange border postValeur0.000.0020.00
    Date
    Observation
  • Decrease in average time to clear Zobue-Mwanza border postValeur0.000.0020.00
    Date
    Observation
  • Decrease in average time to clear Caloume-Dedza border postValeur0.000.0020.00
    Date
    Observation

INDICATEURS DE RÉSULTATS INTERMÉDIAIRES

INDICATEURNIVEAU DE RÉFÉRENCE EN COURS OBJECTIF
  • Length of primary and/or secondary road on or connecting regional truck corridor rehabilitated or upgraded in MalawiValeur0.000.0045.00
    Date1 décembre 20208 septembre 202230 juin 2027
    Observation
  • Number of value chain actors supported by value chain development activities.Valeur0.000.005000.00
    Date1 décembre 20208 septembre 202230 juin 2027
    Observation
  • Reduction in percentage of consignments subject to physical inspection in MalawiValeur70.0070.0040.00
    Date1 décembre 20208 septembre 202230 juin 2027
    Observation
  • Length of secondary or tertiary road connecting to regional truck corridor rehabilitated or upgraded in MozambiqueValeur0.000.00351.00
    Date1 décembre 20208 septembre 202230 juin 2027
    Observation
  • Number of women value chain actors supported by value chain development activitiesValeur0.000.002500.00
    Date1 décembre 20208 septembre 202217 mai 2027
    Observation
  • Number of harmonized standards/mutual recognition agreements/ equivalence arrangements agreed between Malawi and MozambiqueValeur0.002.006.00
    Date1 décembre 20202 octobre 202330 juin 2027
    Observation
  • Reduction in percentage of consignments subject to physical inspection in MozambiqueValeur60.0060.0040.00
    Date1 décembre 20208 septembre 202230 juin 2027
    Observation
  • Mozambique Logistics KPIs publishedValeurNoYesYes
    Date1 décembre 20207 avril 202330 juin 2027
    Observation
  • Gender gap in the share of the value of production soldValeur17.0017.0012.00
    Date1 décembre 20208 septembre 202230 juin 2027
    Observation
  • Reduction in the number of agencies physically located at Dedza and Muloza border posts in MalawiValeur13.0013.006.00
    Date1 décembre 20208 septembre 202230 juin 2027
    Observation
  • Number of blackspot locations improved in MozambiqueValeur0.000.003.00
    Date1 décembre 20208 septembre 202230 juin 2027
    Observation
  • Upgrade infrastructure at all border posts in MozambiqueValeur0.000.00100.00
    Date1 décembre 20208 septembre 202230 juin 2027
    Observation
  • Number of schools with IRAP Star Rating along the Nacala corridorValeur0.000.0051.00
    Date1 décembre 20208 septembre 202230 juin 2027
    Observation
  • Malawi Logistics KPIs publishedValeurNoYesYes
    Date1 décembre 20207 avril 202330 juin 2027
    Observation
  • Spatial information tools developed to monitor civil works projects in areas vulnerable to flood and storms (Climate indicator)ValeurNoYesYes
    Date1 décembre 20202 octobre 202330 juin 2027
    Observation
  • Number of schools with IRAP Star Rating along the Nacala corridor (Mozambique)Valeur0.000.0036.00
    Date1 décembre 20208 septembre 202217 mai 2027
    Observation
  • Grievances responded and/or resolved within the stipulated service standardsValeur0.000.00100.00
    Date1 décembre 20208 septembre 202230 juin 2027
    Observation
  • Number of schools with IRAP Star Rating along the Nacala corridor (Malawi)Valeur0.000.0015.00
    Date1 décembre 20208 septembre 202217 mai 2027
    Observation
  • Increase in small scale cross-border traders (SSCBT) beneficiariesValeur0.000.0025.00
    Date1 décembre 20208 septembre 202230 juin 2027
    Observation
  • Construction of axle load weigh station in MalawiValeur0.000.001.00
    Date1 décembre 20208 septembre 202230 juin 2027
    Observation
  • Grievances responded and/or resolved within the stipulated service standards in MozambiqueValeur0.000.00100.00
    Date1 juin 20218 septembre 202217 mai 2027
    Observation
  • African Road Safety Observatory (ARSO) datasets collected and reported in Malawi and MozambiqueValeurNoNoYes
    Date1 décembre 20208 septembre 202230 juin 2027
    Observation
  • Grievances responded and/or resolved within the stipulated service standards in MalawiValeur0.000.00100.00
    Date1 juin 20218 septembre 202217 mai 2027
    Observation
  • Increase in women small scale cross-border traders (SSCBT) beneficiariesValeur0.000.0025.00
    Date1 décembre 20208 septembre 202217 mai 2027
    Observation