The development objective of the National Hydrology Project for India is to improve the extent, quality, and accessibility of water resources information and to strengthen the capacity of targeted water resources management institutions in India. The project comprises of four components. The first component, water resources monitoring systems will finance the establishment and modernization of new and existing hydromet monitoring systems including...

* Le résumé de projet étant tiré du document d'évaluation de projet (PAD), du rapport d'évaluation (SAR) ou du document du programme (PGD), il peut ne pas refléter exactement la teneur du projet en son état actuel.

Voir plus

Objectif de développement

The proposed Project Development Objective (PDO) is to improve the extent, quality, and accessibility of water resources information and to strengthen the capacity of targeted water resources management institutions in India.

Clé Détails

Projet Détails

  • P152698

  • Active

  • Anju Gaur

  • Ministry of Finance, Department of Economic Affairs

  • Inde

  • 1 janvier 2015

  • (à la date de présentation au Conseil)

    15 mars 2017

  • 5 mai 2017

  • USD 350.00 millions

  • Department of Water Resources, RD & GR, Ministry of Jal Shakti

  • Asie du Sud

  • 2017

  • USD 160.00 millions

  • B

  • 19 mars 2024

  • 31 mars 2025

  • TBD

  • BANK APPROVED

  • Notes

Finances

Plan De Financement (Millions De Dollars)

Pas de données disponibles.
Org. De Financement Engagements
International Bank for Reconstruction and Development 160.00
Borrower/Recipient 175.00

Financement total du projet (USD millions)

Type de produit/service BIRD/IDA
Engagement BIRD 160.00
Engagement IDA N/D
Engagement BIRD + IDA 160.00
Instrument de prêt
Élément don N/D
Coût total du projet** 350.00

État récapitulatif du financement de la Banque (USD millions) au 28 février 2025

Télécharger:
Pas de données disponibles.
Org. De Financement Date D'approbation Date De Cloture Montant En Principal Décaissé Remboursements Intérêts, Charges Et Commissions Financières

Activité financière détaillée au 28 février 2025

Télécharger:
Pas de données disponibles.
Période Org. De Financement Type De Transaction Montant (USD)

Footnotes

Ratings

EXÉCUTION DU PROJET

Name Review Date
Project Management Satisfactory 2024-08-30
Progress towards achievement of PDO Satisfactory 2024-08-30
Monitoring and Evaluation Satisfactory 2024-08-30
Overall Implementation Progress (IP) Satisfactory 2024-08-30
Procurement Satisfactory 2024-08-30
Financial Management Moderately Satisfactory 2024-08-30

FIN D’EXÉCUTION DU PROJET

Pas de données disponibles.

NOTATION DE L’ÉVALUATION INDÉPENDANTE

Pas de données disponibles.

Cadre de résultats

INDICATEURS DES OBJECTIFS DE DÉVELOPPEMENT DU PROJET

INDICATEURNIVEAU DE RÉFÉRENCE EN COURS OBJECTIF
  • Water Resources Institutions achieving benchmark performance levelsValeur0.0017.0015.00
    Date16 mars 201729 février 202431 mars 2025
    Observation
  • Water resources monitoring stations operated by implementing agencies providing validated data onlineValeur0.009766.007630.00
    Date16 mars 201729 février 202431 mars 2025
    Observation
  • Surface water stationsValeur0.001490.001560.00
    Date16 mars 201729 février 202431 mars 2025
    Observation
  • Groundwater stationsValeur0.006440.004690.00
    Date16 mars 201729 février 202431 mars 2025
    Observation
  • Meteorology stationsValeur0.001863.001380.00
    Date16 mars 201729 février 202431 mars 2025
    Observation
  • Information products produced under the project made available to the relevant stakeholdersValeur0.0023.0045.00
    Date16 mars 201729 février 202431 mars 2025
    Observation

INDICATEURS DE RÉSULTATS INTERMÉDIAIRES

INDICATEURNIVEAU DE RÉFÉRENCE EN COURS OBJECTIF
  • Water data centers functioning satisfactorilyValeur0.0025.0020.00
    Date16 mars 201729 février 202431 mars 2025
    Observation
  • Water resources monitoring stations along with historical data standardized and integrated with the national platformValeur0.00102876.0070000.00
    Date15 mars 201729 février 202431 mars 2025
    Observation
  • WRIS users satisfied with the servicesValeur0.0084.0050.00
    Date16 mars 201729 février 202431 mars 2025
    Observation
  • Page views to access the information at WRISValeur400.00800.00900.00
    Date16 mars 201729 février 202431 mars 2025
    Observation
  • Water resources applications developedValeur0.009.0015.00
    Date16 mars 201729 février 202431 mars 2025
    Observation
  • Advanced flood forecasting systems developed for river basinsValeur0.003.007.00
    Date16 mars 201729 février 202431 mars 2025
    Observation
  • Targeted professionals trainedValeur0.001833.002000.00
    Date16 mars 201729 février 202431 mars 2025
    Observation