Org. De Financement | Engagements |
---|---|
IDA Credit | 300.00 |
Borrower/Recipient | 645.00 |
P178136
Active
Ahmed Ousman Abani , Yang Liu
Republic of Cameroon
6 novembre 2022
(à la date de présentation au Conseil)
3 août 2023
27 mars 2024
USD 300.00 millions
Ministry of Water Resources and Energy (MINEE)
2024
USD 300.00 millions
N/A
19 juin 2024
30 juin 2028
Yes
BANK APPROVED
Org. De Financement | Engagements |
---|---|
IDA Credit | 300.00 |
Borrower/Recipient | 645.00 |
Type de produit/service | BIRD/IDA |
---|---|
Engagement BIRD | N/D |
Engagement IDA | 300.00 |
Engagement BIRD + IDA | 300.00 |
Instrument de prêt | |
---|---|
Élément don | N/D |
Coût total du projet** | 300.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2024-12-23 |
Monitoring and Evaluation | Satisfactory | 2024-12-23 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-12-23 |
INDICATEUR | NIVEAU DE RÉFÉRENCE | EN COURS | OBJECTIF |
---|
Reduction of annual revenue gap between maximum allowed revenues and tariff revenues | Valeur | 9.50 | 9.50 | 5.00 |
Date | 1 juillet 2022 | 10 juin 2024 | 31 décembre 2027 | |
Observation |
Public disclosure of annual audits of ENEO and SONATREL performance reports | Valeur | Absence of systematic regulatory audit of performa | Absence of systematic regulatory audit of performa | ARSEL has published a report on technical audit of |
Date | 1 juillet 2022 | 10 juin 2024 | 31 décembre 2027 | |
Observation |
People provided with new or improved electricity service | Valeur | 0.00 | 0.00 | 1055000.00 |
Date | 1 juillet 2022 | 10 juin 2024 | 31 décembre 2027 | |
Observation |
Timely payments of public administration’s electricity consumption and annual compensation | Valeur | Irregular payments of annual compensation and elec | Irregular payments of annual compensation and elec | (a) 100% of the budgeted amount of tariff compensa |
Date | 1 juillet 2022 | 10 juin 2024 | 31 mars 2028 | |
Observation |
People provided with new or improved electricity service - Female | Valeur | 0.00 | 0.00 | 101000.00 |
Date | ||||
Observation |
INDICATEUR | NIVEAU DE RÉFÉRENCE | EN COURS | OBJECTIF |
---|
ARSEL has issued an annual resolution setting MAR of ENEO and SONATREL | Valeur | Lack of systematic issuance of resolution setting | Lack of systematic issuance of resolution setting | ARSEL has issued an annual resolution setting MAR |
Date | 6 janvier 2023 | 10 juin 2024 | 31 décembre 2027 | |
Observation |
Women interns in technical internships | Valeur | 15.00 | 15.00 | 30.00 |
Date | 6 janvier 2023 | 10 juin 2024 | 31 décembre 2027 | |
Observation |
Households provided with new electricity service | Valeur | 0.00 | 0.00 | 211000.00 |
Date | 6 janvier 2023 | 10 juin 2024 | 31 décembre 2027 | |
Observation |
Annual compensation amount estimated and included into National Budget Law | Valeur | Non-regular inclusion of compensation amount in An | ARSEL has issued a resolution establishing a proce | ARSEL has communicated timely to MINFI the estimat |
Date | 6 janvier 2023 | 10 juin 2024 | 31 décembre 2027 | |
Observation |
Women accessing energy sector jobs/promotion following internship | Valeur | 5.00 | 5.00 | 20.00 |
Date | 6 janvier 2023 | 10 juin 2024 | 31 décembre 2027 | |
Observation |
Increase in renewable electricity supply to grid-connected and mini-grid consumers | Valeur | 0.00 | 0.00 | 44.60 |
Date | 6 janvier 2023 | 10 juin 2024 | 31 décembre 2027 | |
Observation |
Smart meters installed and put in service to record consumption of public facilities | Valeur | 0.00 | 0.00 | 15000.00 |
Date | 6 janvier 2023 | 10 juin 2024 | 31 décembre 2027 | |
Observation |
Grievances registered and addressed within the GRM timeframe | Valeur | 0.00 | 0.00 | 100.00 |
Date | 6 janvier 2023 | 10 juin 2024 | 31 décembre 2027 | |
Observation |
Increase in transformation capacity in transmission system | Valeur | 2898000.00 | 2898000.00 | 3136900.00 |
Date | 6 janvier 2023 | 10 juin 2024 | 31 décembre 2027 | |
Observation |
Public lamps with metered consumption | Valeur | 0.00 | 0.00 | 150000.00 |
Date | 6 janvier 2023 | 10 juin 2024 | 31 décembre 2027 | |
Observation |
Net greenhouse gas (GHG) emissions | Valeur | 0.00 | 0.00 | 168000.00 |
Date | 6 janvier 2023 | 10 juin 2024 | 31 décembre 2027 | |
Observation |