Skip to Main Navigation

Access Governance & Reform for the Electricity and Water Sectors Project

Résumé*

The project aims to significantly scale up access to electricity and water services in priority areas of the DRC while improving utility governance and performance and strengthening public institution capacity. It will target ten provinces prioritized in the Country Partnership Framework 2022-2026. Project components 1 and 2 will address market failures (e.g., tariffs, regulations), support upstream SNEL reform and REGIDESO restructuring, and strengthen...

* Le résumé de projet étant tiré du document d'évaluation de projet (PAD), du rapport d'évaluation (SAR) ou du document du programme (PGD), il peut ne pas refléter exactement la teneur du projet en son état actuel.

Voir plus

Objectif de développement

The objectives of the Project are to (i) expand access to renewable-based electricity and drinking water services in selected urban and peri-urban areas of the Democratic Republic of Congo, (ii) improve the commercial performance of the public electricity and water utilities, and (iii) strengthen the capacity of selected provincial and national institutions in the electricity and water sector.

Clé Détails

Projet Détails

  • P173506

  • Active

  • Didier Tsasa , Fabrice Bertholet, Patrick Ndolo

  • DEMOCRATIC REPUBLIC OF CONGO

  • Congo, République démocratique du

  • 6 janvier 2021

  • (à la date de présentation au Conseil)

    31 mars 2022

  • 18 mai 2023

  • USD 939.00 millions

  • Ministère des Ressources Hydrauliques et de l'Electricité (MHRE)

  • Eastern and Southern Africa

  • 2022

  • USD 634.00 millions

  • N/A

  • 17 juin 2024

  • 30 septembre 2029

  • Yes

  • BANK APPROVED

  • Notes

Finances

Plan De Financement (Millions De Dollars)

Pas de données disponibles.
Org. De Financement Engagements
Green Climate Fund 34.00
IDA Credit 300.00
IDA Grant 300.00

Financement total du projet (USD millions)

Type de produit/service BIRD/IDA
Engagement BIRD N/D
Engagement IDA 600.00
Engagement BIRD + IDA 600.00
Instrument de prêt
Élément don 34.00
Coût total du projet** 939.00

État récapitulatif du financement de la Banque (USD millions) au 31 mars 2025

Télécharger:
Pas de données disponibles.
Org. De Financement Date D'approbation Date De Cloture Montant En Principal Décaissé Remboursements Intérêts, Charges Et Commissions Financières

Activité financière détaillée au 31 mars 2025

Télécharger:
Pas de données disponibles.
Période Org. De Financement Type De Transaction Montant (USD)

Footnotes

Ratings

EXÉCUTION DU PROJET

Name Review Date
Procurement Moderately Satisfactory 2024-09-20
Project Management Moderately Unsatisfactory 2024-09-20
Financial Management Moderately Unsatisfactory 2024-09-20
Overall Implementation Progress (IP) Moderately Unsatisfactory 2024-09-20
Progress towards achievement of PDO Moderately Unsatisfactory 2024-09-20
Monitoring and Evaluation Satisfactory 2024-09-20

FIN D’EXÉCUTION DU PROJET

Pas de données disponibles.

NOTATION DE L’ÉVALUATION INDÉPENDANTE

Pas de données disponibles.

Cadre de résultats

INDICATEURS DES OBJECTIFS DE DÉVELOPPEMENT DU PROJET

INDICATEURNIVEAU DE RÉFÉRENCE EN COURS OBJECTIF
  • People provided with new or improved electricity serviceValeur0.000.006000000.00
    Date30 septembre 202225 avril 202428 septembre 2029
    Observation
  • SNEL bill collection rateValeur60.0060.0080.00
    Date30 septembre 202225 avril 202428 septembre 2029
    Observation
  • Operating ratio for REGIDESO subsidiariesValeur0.000.001.10
    Date30 septembre 202225 avril 202428 septembre 2029
    Observation
  • Nord Kivu and Kasai Central Provincial Infrastructure Units responsible for water and electricity established and operationalValeurno dedicated units under the provincial governmentProvincial Water Unit put in place in North-KivuProvincial infrastructure units operational in Kas
    Date30 septembre 202225 avril 202428 septembre 2029
    Observation
  • People provided with new or improved electricity service - FemaleValeur0.000.0090000.00
    Date
    Observation
  • People provided with access to at least basic water supply servicesValeur0.000.00680000.00
    Date30 septembre 202225 avril 202428 septembre 2029
    Observation
  • Water sector regulator (ARSPE) capacity strengthenedValeurARSPE not operationalNo Manager and staff appointedARSPE with trained staff, tariff model, standard c
    Date30 septembre 202225 avril 202430 septembre 2029
    Observation
  • Operating ratio for REGIDESO Nord KivuValeur0.000.001.10
    Date29 septembre 202225 avril 202429 septembre 2029
    Observation
  • Energy regulator (ARE) capacity strengthenedValeurlimited staff, no tariff model and database/MISPermanent staff appointedARE with trained staff, tariff model, standard con
    Date30 septembre 202225 avril 202430 septembre 2029
    Observation
  • Operating ratio for REGIDESO Kasai OccidentalValeur0.000.001.10
    Date29 septembre 202225 avril 202429 septembre 2029
    Observation
  • out of which femaleValeur0.000.00290000.00
    Date30 septembre 202225 avril 202428 septembre 2029
    Observation
  • of which basic water servicesValeur0.000.0015000.00
    Date
    Observation
  • of which safely managed water servicesValeur0.000.0015000.00
    Date
    Observation

INDICATEURS DE RÉSULTATS INTERMÉDIAIRES

INDICATEURNIVEAU DE RÉFÉRENCE EN COURS OBJECTIF
  • Battery storage for renewable energy installedValeur0.000.000.00
    Date
    Observation
  • among femalesValeur0.000.0080.00
    Date30 septembre 202225 avril 202430 septembre 2029
    Observation
  • Tariff adjustments for REGIDESO subsidiaries approved and satisfactory government agencies' bill payment to REGIDESO subsidiaries in Nord Kivu and Kasai CentralValeurNoNoYes
    Date30 septembre 202225 avril 202428 septembre 2029
    Observation
  • Annual GHG emissions reduced resulting from mini-grid development and operationValeur0.000.00800000.00
    Date30 septembre 202225 avril 202430 septembre 2029
    Observation
  • Households provided with access to at least basic water services by private operatorsValeur0.000.0044300.00
    Date30 septembre 202225 avril 202428 septembre 2029
    Observation
  • out of which households with basic water servicesValeur0.000.001200.00
    Date
    Observation
  • out of which households with safely managed water serviceValeur0.000.00800.00
    Date
    Observation
  • Households provided with at least basic water services by public operatorsValeur0.000.0069000.00
    Date30 septembre 202225 avril 202428 septembre 2029
    Observation
  • out of which basic water servicesValeur0.000.001300.00
    Date
    Observation
  • Private capital mobilized from private mini-grid developers through risk mitigation instrumentValeur0.000.00120000.00
    Date30 septembre 202225 avril 202430 septembre 2029
    Observation
  • out of which safely managed water servicesValeur0.000.001700.00
    Date
    Observation
  • Fecal sludge delivered to treatment plants and disposed safelyValeur0.000.0060000.00
    Date30 septembre 202225 avril 202428 septembre 2029
    Observation
  • Health centers and schools with electricity and WASH facilities installedValeur0.000.00250.00
    Date30 septembre 202225 avril 202428 septembre 2029
    Observation
  • Public WASH facilities rehabilitated/constructed with electricity and a private O&M arrangementValeur0.000.00500.00
    Date30 septembre 202225 avril 202428 septembre 2029
    Observation
  • Including share managed by female entrepreneursValeur0.000.0040.00
    Date
    Observation
  • Tariff adjustment methodology approved and SNEL's tariffs adjustedValeurNoNoYes
    Date30 septembre 202225 avril 202428 septembre 2029
    Observation
  • Water Resources Management Agency (OCE) operational and branch in Kasai Central establishedValeurOCE created Nov 2021, but not operationalNo staff appointed and OCE no operationalOCE strengthened (including Kasai branch, with Wat
    Date30 septembre 202225 avril 202428 septembre 2029
    Observation
  • On/off-grid household electricity connections from private operatorsValeur0.000.00350000.00
    Date30 septembre 202225 avril 202428 septembre 2029
    Observation
  • New household electricity connectionsValeur0.000.0080000.00
    Date30 septembre 202225 avril 202428 septembre 2029
    Observation
  • Electricity/water bills of government agencies are paid timely; free electricity/water consumption by public officials is reducedValeurNoNoYes
    Date30 septembre 202225 avril 202430 septembre 2029
    Observation
  • Draft Sanitation Act is proposed for government review and parliamentary approvalValeurNoNoYes
    Date30 septembre 202225 avril 202428 septembre 2029
    Observation
  • On/off-grid productive and community user connectionsValeur0.000.003000.00
    Date30 septembre 202225 avril 202428 septembre 2029
    Observation
  • Improved household electricity connectionsValeur0.000.00320000.00
    Date30 septembre 202225 avril 202428 septembre 2029
    Observation
  • SNEL uses MIS with electronic payment, establishes a Network Maintenance Fund and signs a PPP contract for Network O&MValeurNoNoYes
    Date30 septembre 202225 avril 202428 septembre 2029
    Observation
  • Share of beneficiaries in the project areas satisfied with feedback opportunities and grievance resolutionValeur0.000.0080.00
    Date30 septembre 202225 avril 202428 septembre 2029
    Observation
  • Renewable energy capacity constructed or rehabilitatedValeur0.000.0025.00
    Date30 septembre 202225 avril 202428 septembre 2029
    Observation
  • Two REGIDESO subsidiaries operational under public service delegation contracts with provinces of Nord Kivu and Kasai CentralValeurNoNoYes
    Date30 septembre 202225 avril 202428 septembre 2029
    Observation
  • Share of new positions/jobs within electricity and water entities that are taken by women (public and private)Valeur0.000.0030.00
    Date30 septembre 202225 avril 202430 septembre 2029
    Observation
  • Out of which in technical positionsValeur0.000.000.00
    Date
    Observation