Nile Cooperation for Climate Resilience

Résumé*

The proposed project builds on a long-term technical engagement with the NBI, LVBC and NBD . The concept proposed scales up certain types of actions and engagements where these regional organizations have been successful in mobilizing countries around cooperative action and where countries have expressed interest and need for further engagement. Bringing the organizations together will enable them to complement each other further effectiveness and...

* Le résumé de projet étant tiré du document d'évaluation de projet (PAD), du rapport d'évaluation (SAR) ou du document du programme (PGD), il peut ne pas refléter exactement la teneur du projet en son état actuel.

Voir plus

Objectif de développement

The project development objective is to improve mechanisms for cooperation on water resources management and development in the Nile Basin.

Clé Détails

Projet Détails

  • P172848

  • Active

  • Shyam KC , Kimberly Lyon, Lars Jagerskog

  • Nile Basin Initiative Secretariat

  • Eastern and Southern Africa

  • 7 avril 2020

  • (à la date de présentation au Conseil)

    27 février 2021

  • 11 mars 2021

  • USD 30.00 millions

  • East African Community through Lake Victoria Basin Commission,Nile Equitorial Lakes Subsidiary Action Program - Coordination Unit,Nile Basin Discourse,Eastern Nile Regional Technical Organization

  • Eastern and Southern Africa

  • 2021

  • USD 30.00 millions

  • N/A

  • 14 février 2024

  • 30 novembre 2025

  • Yes

  • BANK APPROVED

  • Notes

Finances

Plan De Financement (Millions De Dollars)

Pas de données disponibles.
Org. De Financement Engagements
Cooperation in International Waters in Africa 30.00

Financement total du projet (USD millions)

Type de produit/service BIRD/IDA
Engagement BIRD N/D
Engagement IDA N/D
Engagement BIRD + IDA N/D
Instrument de prêt
Élément don 30.00
Coût total du projet** 30.00

État récapitulatif du financement de la Banque (USD millions) au 31 mars 2025

Télécharger:
Pas de données disponibles.
Org. De Financement Date D'approbation Date De Cloture Montant En Principal Décaissé Remboursements Intérêts, Charges Et Commissions Financières

Activité financière détaillée au 31 mars 2025

Télécharger:
Pas de données disponibles.
Période Org. De Financement Type De Transaction Montant (USD)

Footnotes

Ratings

EXÉCUTION DU PROJET

Name Review Date
Progress towards achievement of PDO Satisfactory 2024-11-30
Project Management Satisfactory 2024-11-30
Financial Management Satisfactory 2024-11-30
Procurement Moderately Satisfactory 2024-11-30
Monitoring and Evaluation Moderately Satisfactory 2024-11-30
Overall Implementation Progress (IP) Moderately Satisfactory 2024-11-30

FIN D’EXÉCUTION DU PROJET

Pas de données disponibles.

NOTATION DE L’ÉVALUATION INDÉPENDANTE

Pas de données disponibles.

Cadre de résultats

INDICATEURS DES OBJECTIFS DE DÉVELOPPEMENT DU PROJET

INDICATEURNIVEAU DE RÉFÉRENCE EN COURS OBJECTIF
  • Number of joint governance decisions informed by results from project supported activitiesValeur0.004.0010.00
    Date26 février 202122 novembre 202328 novembre 2025
    Observation
  • Percentage of users of mechanisms for cooperation on water resources management and development, who rate them as “satisfactory” orhigherValeur0.0092.0080.00
    Date26 février 202122 novembre 202328 novembre 2025
    Observation

INDICATEURS DE RÉSULTATS INTERMÉDIAIRES

INDICATEURNIVEAU DE RÉFÉRENCE EN COURS OBJECTIF
  • Number of people trainedValeur0.002014.00900.00
    Date26 février 202122 novembre 202328 novembre 2025
    Observation
  • Number of new or improved dam safety unitsValeur5 dam safety units exist in Nile Basin countries5 existing DSU’s are improved (Ethiopia, Kenya, Su4 new dam safety unit are established. 5 dam safet
    Date26 février 202122 novembre 202328 novembre 2025
    Observation
  • Enhanced flood and drought information available in the public domainValeurnoneMapping of riverine flood prone areas in the Nile Enhanced flood and drought information available i
    Date26 février 202122 novembre 202328 novembre 2025
    Observation
  • Number of community level stakeholders consulted for usability of flood warning notificationsValeur0.00616.00750.00
    Date26 février 202122 novembre 202328 novembre 2025
    Observation
  • Number of Instruments developed to guide/govern water quality investment planning in the Lake Victoria Basin/NEL regionValeurzeroOne draft regional harmonized policy2 instruments: (i) A draft harmonized policy on wa
    Date26 février 202122 novembre 202328 novembre 2025
    Observation
  • Mechanisms for increasing equivalence in regional dam safety management developedValeurNoneNoneMechanisms for increasing equivalence in regional
    Date26 février 202122 novembre 202328 janvier 2025
    Observation
  • Number of institutions consulted to enhance or monitor usability of flood related informationValeur0.003.0020.00
    Date26 février 202122 novembre 202328 novembre 2025
    Observation
  • number of womenValeur0.00406.00225.00
    Date26 février 202122 novembre 202328 novembre 2025
    Observation
  • number of womenValeur0.00180.00300.00
    Date26 février 202122 novembre 202328 novembre 2025
    Observation
  • Number of Water Quality Hotspots where investment prioritization is supported by stakeholder dialogue and relevant analysisValeur02 Water Quality Hotspot investment prioritization 4 Water Quality Hotspots for which investment prio
    Date26 février 202122 novembre 202328 novembre 2025
    Observation
  • Total number of interns/Young ProfessionalValeur0.0040.0048.00
    Date26 février 202122 novembre 202328 janvier 2025
    Observation
  • number from fragile or conflict affected situationsValeur0.00861.00225.00
    Date26 février 202122 novembre 202328 novembre 2025
    Observation
  • number from fragile or conflict affected situationsValeur0.00257.00300.00
    Date26 février 202122 novembre 202328 novembre 2025
    Observation
  • Number of fit-for-purpose networks created or strengthened.Valeur0.0022.0010.00
    Date26 février 202122 novembre 202328 novembre 2025
    Observation
  • Number of womenValeur0.0011.0015.00
    Date26 février 202122 novembre 202328 novembre 2025
    Observation
  • Number of stakeholders directly supported on applications of the Nile Basin Data Analytics ServicesValeur0.00346.00200.00
    Date26 février 202124 mai 202328 novembre 2025
    Observation
  • Number from Fragile and Conflict affected SituationsValeur0.0028.0024.00
    Date26 février 202122 novembre 202328 novembre 2025
    Observation
  • Number of mechanisms for cooperation improved with open platform public data productsValeur0.001.004.00
    Date26 février 202122 novembre 202328 novembre 2025
    Observation