Morocco Urban Transport Project (P4R)

Résumé*

The development objective of the Program-for-Results (PforR) Urban Transport Program Project for Morocco is to strengthen the capacity of urban transport institutions to plan, implement, and monitor infrastructure and services, and to improve the level of service of urban transport in targeted corridors in the program area. It will support the country partnership strategy (CPS) results area promoting competitive and inclusive growth by better linking...

* Le résumé de projet étant tiré du document d'évaluation de projet (PAD), du rapport d'évaluation (SAR) ou du document du programme (PGD), il peut ne pas refléter exactement la teneur du projet en son état actuel.

Voir plus

Objectif de développement

The Program Development Objective is to strengthen the capacity of urban transport institutions to plan, implement and monitor infrastructure and services, and to improve the level of service of urban transport in targeted corridors in the Program Area.

Clé Détails

Projet Détails

  • P149653

  • Active

  • Nabil Samir , Clotilde Minster

  • Kingdom of Morocco

  • Maroc

  • 16 juin 2015

  • (à la date de présentation au Conseil)

    9 décembre 2015

  • 15 janvier 2016

  • USD 700.00 millions

  • Ministry of Interior - General Directorate for Territorial Government

  • Moyen-Orient et Afrique du Nord

  • 2016

  • USD 200.00 millions

  • N/A

  • 24 juin 2024

  • 31 décembre 2025

  • BANK APPROVED

  • Notes

Finances

Plan De Financement (Millions De Dollars)

Pas de données disponibles.
Org. De Financement Engagements
Borrower/Recipient 150.00
International Bank for Reconstruction and Development 200.00

Financement total du projet (USD millions)

Type de produit/service BIRD/IDA
Engagement BIRD 200.00
Engagement IDA N/D
Engagement BIRD + IDA 200.00
Instrument de prêt
Élément don N/D
Coût total du projet** 700.00

État récapitulatif du financement de la Banque (USD millions) au 31 mars 2025

Télécharger:
Pas de données disponibles.
Org. De Financement Date D'approbation Date De Cloture Montant En Principal Décaissé Remboursements Intérêts, Charges Et Commissions Financières

Activité financière détaillée au 31 mars 2025

Télécharger:
Pas de données disponibles.
Période Org. De Financement Type De Transaction Montant (USD)

Footnotes

Ratings

EXÉCUTION DU PROJET

Name Review Date
Overall Implementation Progress (IP) Satisfactory 2025-01-10
Progress towards achievement of PDO Moderately Satisfactory 2025-01-10
Monitoring and Evaluation Satisfactory 2025-01-10

FIN D’EXÉCUTION DU PROJET

Pas de données disponibles.

NOTATION DE L’ÉVALUATION INDÉPENDANTE

Pas de données disponibles.

Cadre de résultats

INDICATEURS DES OBJECTIFS DE DÉVELOPPEMENT DU PROJET

INDICATEURNIVEAU DE RÉFÉRENCE EN COURS OBJECTIF
  • Number of cities (with more than 100,000 inhabitants) that improved their urban transport institutional assessment score by at least 10 percentValeur0.0029.0027.00
    Date1 janvier 201619 juin 202430 juin 2024
    Observation
  • Percentage of corridors in the Priority Program of Corridors (PPC) supported under the Program that meet their objectives in reduction of urban transport journey timeValeur0.0047.0095.00
    Date1 janvier 201619 juin 202430 juin 2024
    Observation

INDICATEURS DE RÉSULTATS INTERMÉDIAIRES

INDICATEURNIVEAU DE RÉFÉRENCE EN COURS OBJECTIF
  • Strengthened Urban Transport FundValeurThe institutional and financial arrangements of thActions identified under DLR #2.6 have been carrieThe Urban Transport Fund has been strengthened to
    Date1 janvier 201619 juin 202430 juin 2024
    Observation
  • Number of urban mobility master plans prepared using a structured process and a participatory approachValeur3.008.009.00
    Date1 janvier 201619 juin 202430 juin 2024
    Observation
  • Percentage of progress in the execution of the Priority Program of CorridorsValeur0.00100.000.00
    Date
    Observation
  • Number of operational municipality-owned urban transport enterprisesValeur2.005.006.00
    Date1 janvier 201619 juin 202430 juin 2024
    Observation
  • Percentage of corridors supported by the Program that meet their time saving objectivesValeur0.0047.0095.00
    Date1 janvier 201619 juin 202430 juin 2024
    Observation
  • Direct Program beneficiariesValeur0.00100000.00150000.00
    Date1 janvier 201619 juin 202430 juin 2024
    Observation
  • of which femaleValeur0.0040.0050.00
    Date1 janvier 201619 juin 202430 juin 2024
    Observation
  • User satisfaction rate (percentage) for the implemented corridors, disaggregated by genderValeur0.000.0075.00
    Date30 juin 202019 juin 202430 juillet 2024
    Observation
  • of which femaleValeur0.000.0080.00
    Date30 juin 202019 juin 202430 juin 2024
    Observation
  • of which maleValeur0.000.0070.00
    Date30 juin 202019 juin 202430 juin 2024
    Observation
  • Awarding, extension or amendment as needed of urban mobility concessions for implemented corridorsValeurNoNoYes
    Date30 juin 202019 juin 202430 juin 2024
    Observation
  • Deployment of an operational Grievance Redress Mechanism (GRM) for the operations of implemented corridorsValeurNoYesYes
    Date30 juin 202019 juin 202430 juin 2024
    Observation
  • Preparation and implementation of gender action plans for urban transport at the local levelValeurNoNoYes
    Date30 juin 202019 juin 202430 juin 2024
    Observation
  • Change in the share of female ridership in targeted corridorsValeur0.000.0010.00
    Date30 juin 202019 juin 202430 juin 2024
    Observation
  • Cumulative GHG emission saved (in tons) as a result of the ProgramValeur0.008500.0010000.00
    Date30 juin 202019 juin 202430 juin 2024
    Observation
  • Strengthened M&E system for the urban transport sectorValeurCurrent M&E system is paper-based and limited in sActions identified under DLR #1.7 have been carrieNational M&E, coordination, and support for the ur
    Date1 janvier 201619 juin 202430 juin 2024
    Observation
  • Number of operational associations of urban agglomerationsValeur0.005.005.00
    Date1 janvier 201619 juin 202430 juin 2024
    Observation
  • Percentage of Priority Program of Corridors completed and open to trafficValeur0.0023.0050.00
    Date1 janvier 201619 juin 202430 juin 2024
    Observation