Community Development Program Support Project-Phase III

Résumé*

The development objective of the Third Phase of the Community Development Program Support Project for Cameroon is to strengthen local public finance management and participatory development processes in communes for the delivery of quality and sustainable social and economic infrastructure. The project comprises of three components. The first component, local development support will ensure equity, the project authorities will allocate funds to communes...

* Le résumé de projet étant tiré du document d'évaluation de projet (PAD), du rapport d'évaluation (SAR) ou du document du programme (PGD), il peut ne pas refléter exactement la teneur du projet en son état actuel.

Voir plus

Objectif de développement

The development objective of phase 3 (PNDP III) is to strengthen local public finance management and participatory development processes in communes for the delivery of quality and sustainable social and economic infrastructure.

Clé Détails

Projet Détails

  • P144637

  • Closed

  • Abderrahim Fraiji , Issa Bitang A Tiati

  • REPUBLIC OF CAMEROON

  • Cameroun

  • 11 décembre 2014

  • (à la date de présentation au Conseil)

    29 septembre 2015

  • 1 avril 2016

  • USD 133.00 millions

  • Republic of Cameroon

  • Western and Central Africa

  • 2016

  • USD 70.00 millions

  • B

  • 26 mars 2024

  • 30 juin 2024

  • TBD

  • BANK APPROVED

  • Notes

Finances

Plan De Financement (Millions De Dollars)

Pas de données disponibles.
Org. De Financement Engagements
IDA Credit 70.00
Local Beneficiaries 7.00
Borrower/Recipient 56.00

Financement total du projet (USD millions)

Type de produit/service BIRD/IDA
Engagement BIRD N/D
Engagement IDA 70.00
Engagement BIRD + IDA 70.00
Instrument de prêt
Élément don N/D
Coût total du projet** 133.00

État récapitulatif du financement de la Banque (USD millions) au 31 mars 2025

Télécharger:
Pas de données disponibles.
Org. De Financement Date D'approbation Date De Cloture Montant En Principal Décaissé Remboursements Intérêts, Charges Et Commissions Financières

Activité financière détaillée au 31 mars 2025

Télécharger:
Pas de données disponibles.
Période Org. De Financement Type De Transaction Montant (USD)

Footnotes

Ratings

EXÉCUTION DU PROJET

Name Review Date
Progress towards achievement of PDO Moderately Unsatisfactory 2022-03-01
Procurement Moderately Satisfactory 2022-03-01
Counterpart Funding Unsatisfactory 2022-03-01
Financial Management Moderately Unsatisfactory 2022-03-01
Overall Implementation Progress (IP) Moderately Unsatisfactory 2022-03-01
Monitoring and Evaluation Moderately Satisfactory 2022-03-01
Project Management Moderately Satisfactory 2022-03-01

FIN D’EXÉCUTION DU PROJET

INDICATEURBILAN DE FIN D’EXÉCUTION ET DE RÉSULTATS:
Résultats
Risques pour les résultats de développement
Performance de la Banque
Performance de l'emprunteur
Performance de l’État
Organisme d'exécution

NOTATION DE L’ÉVALUATION INDÉPENDANTE

INDICATEUREXAMEN RFE: 02-03-2025RAPPORT D’ÉVALUATION RÉTROSPECTIVE DE PROJET:
Évaluation Des RésultatsModerately Unsatisfactory N/a
Risques Pour Les Résultats De DéveloppementN/a
Performance De La BanqueModerately UnsatisfactoryN/a
Performance De L'emprunteurN/a
Performance De L’étatN/a
Organisme D'exécutionN/a
Qualité Des RfeModestN/a
Qualité Du Suivi-évaluationModestN/a

Cadre de résultats

INDICATEURS DES OBJECTIFS DE DÉVELOPPEMENT DU PROJET

INDICATEURNIVEAU DE RÉFÉRENCE EN COURS OBJECTIF
  • Percentage of communes having obtained at least the mid-point score in the Guichet PerformanceValeur24.0042.0030.00
    Date1 juin 201730 juin 2022
    Observation
  • Direct project beneficiaries (non refugees)Valeur0.004532649.00800000.00
    Date29 septembre 201530 juin 2022
    Observation
  • Share of Decentralized Public Investment Budget projects derived from Local Development PlansValeur58.8087.2170.00
    Date1 mars 201630 juin 20221 mai 2018
    Observation
  • Female beneficiaries (non-refugees)Valeur0.0020.3935.00
    Date29 septembre 201531 mai 2018
    Observation
  • Beneficiaries that feel project investments reflected their needs (percentage)Valeur91.5087.0060.00
    Date29 septembre 201530 juin 2022
    Observation
  • Beneficiaries that feel project inv. reflected their needs - female (percentage)Valeur0.000.0065.00
    Date29 septembre 201530 novembre 2017
    Observation
  • Direct Project beneficiary (refugees)Valeur0.00515327.00100000.00
    Date28 février 201830 juin 2022
    Observation
  • of which female (refugees)Valeur0.00268112.0035.00
    Date28 février 201830 juin 2022
    Observation

INDICATEURS DE RÉSULTATS INTERMÉDIAIRES

INDICATEURNIVEAU DE RÉFÉRENCE EN COURS OBJECTIF
  • Subprojects that have implemented the required environmental and social risk mitigation measures and are functionalValeur0.0064.72100.00
    Date30 juin 201530 juin 2022
    Observation
  • Communes with a public information and citizen control mechanism on service delivery (citizens scorecards)Valeur10.00341.00360.00
    Date30 juin 201530 juin 20221 mai 2018
    Observation
  • Grievances registered related to delivery of project benefits addressed (%)Valeur0.0096.4790.00
    Date30 juin 201530 juin 20221 mai 2018
    Observation
  • Improved community water points constructed or rehabilitated under the projectValeur1721.00797.004519.00
    Date30 juin 201530 juin 20221 mai 2018
    Observation
  • Number of beneficiaries trainedValeur1720.008304.004200.00
    Date30 juin 201531 mars 20201 mai 2018
    Observation
  • Village Development Committee of host villages with at least one refugee represented in the comittee/bureauValeur0.007.1675.00
    Date28 février 201830 juin 2022
    Observation
  • Roads rehabilitated, RuralValeur465.00117.581063.00
    Date30 juin 201530 juin 20221 mai 2018
    Observation
  • Percentage of communes with at least 30% villages having implemented endogenous solutionsValeur0.0034.5635.00
    Date28 février 201830 juin 2022
    Observation
  • of which femaleValeur50.001031.0035.00
    Date30 juin 201531 mars 2020
    Observation
  • Classrooms built and/or rehabilitatedValeur971.001014.002525.00
    Date30 juin 201530 juin 20221 mai 2018
    Observation
  • Health facilities constructed, renovated or equippedValeur38.0076.00211.00
    Date30 juin 201530 juin 20221 mai 2018
    Observation
  • Rural markets constructed under the projectValeur12.0099.0097.00
    Date30 juin 201530 juin 20221 mai 2018
    Observation
  • Community storage facilities constructed under the projectValeur34.0033.0097.00
    Date30 juin 201530 juin 20221 mai 2018
    Observation
  • Communes benefiting from the project grantValeur328.00311.00360.00
    Date30 juin 201530 juin 2022
    Observation