Résumé*

The development objectives of the Relaunching agriculture second strengthening agriculture public services project for Republic of Haiti are to strengthen the Ministry of Agriculture, Natural Resources and Rural Development's (MARNDR) capacity to define and implement the National Agriculture Extension Strategy, to increase access of small farmers to agriculture extension services and training on animal and plant health in priority regions, and to...

* Le résumé de projet étant tiré du document d'évaluation de projet (PAD), du rapport d'évaluation (SAR) ou du document du programme (PGD), il peut ne pas refléter exactement la teneur du projet en son état actuel.

Voir plus

Objectif de développement

The new proposed PDO is: to (a) reinforce the capacity of the Ministry of Agriculture, Natural Resources and Rural Development to provide or facilitate access to services in the agricultural sector; (b) increase market access to small producers and food security in Selected Areas; (c) improve livelihood in areas affected by Hurricane Matthew and (d) enable the Government to respond promptly and effectively to an eligible emergency.

Clé Détails

Projet Détails

  • P126744

  • Closed

  • Ziva Razafintsalama , Soulemane Fofana

  • Republic of Haiti

  • Haïti

  • 8 août 2011

  • (à la date de présentation au Conseil)

    1 décembre 2011

  • 3 avril 2012

  • USD 50.00 millions

  • Ministry of Agriculture, Natural Resources and Rural Development

  • Amérique latine et Caraïbes

  • 2012

  • USD 50.00 millions

  • B

  • 2 novembre 2023

  • 31 mars 2022

  • BANK APPROVED

  • Notes

Finances

Plan De Financement (Millions De Dollars)

Pas de données disponibles.
Org. De Financement Engagements
Global Agriculture and Food Security Program 10.00
IDA Grant 40.00

Financement total du projet (USD millions)

Type de produit/service BIRD/IDA
Engagement BIRD N/D
Engagement IDA 40.00
Engagement BIRD + IDA 40.00
Instrument de prêt
Élément don 10.00
Coût total du projet** 50.00

État récapitulatif du financement de la Banque (USD millions) au 31 mars 2025

Télécharger:
Pas de données disponibles.
Org. De Financement Date D'approbation Date De Cloture Montant En Principal Décaissé Remboursements Intérêts, Charges Et Commissions Financières

Activité financière détaillée au 31 mars 2025

Télécharger:
Pas de données disponibles.
Période Org. De Financement Type De Transaction Montant (USD)

Footnotes

Ratings

EXÉCUTION DU PROJET

Name Review Date
Procurement Satisfactory 2022-04-08
Overall Implementation Progress (IP) Satisfactory 2022-04-08
Progress towards achievement of PDO Satisfactory 2022-04-08
Project Management Satisfactory 2022-04-08
Financial Management Satisfactory 2022-04-08
Monitoring and Evaluation Satisfactory 2022-04-08

FIN D’EXÉCUTION DU PROJET

INDICATEURBILAN DE FIN D’EXÉCUTION ET DE RÉSULTATS: 11-21-2022
RésultatsSubstantial
Risques pour les résultats de développement
Performance de la BanqueSubstantial
Performance de l'emprunteur
Performance de l’État
Organisme d'exécution

NOTATION DE L’ÉVALUATION INDÉPENDANTE

INDICATEUREXAMEN RFE: 06-14-2023RAPPORT D’ÉVALUATION RÉTROSPECTIVE DE PROJET:
Évaluation Des RésultatsSatisfactory N/a
Risques Pour Les Résultats De DéveloppementN/a
Performance De La BanqueSatisfactoryN/a
Performance De L'emprunteurN/a
Performance De L’étatN/a
Organisme D'exécutionN/a
Qualité Des RfeHighN/a
Qualité Du Suivi-évaluationSubstantialN/a

Cadre de résultats

INDICATEURS DES OBJECTIFS DE DÉVELOPPEMENT DU PROJET

INDICATEURNIVEAU DE RÉFÉRENCE EN COURS OBJECTIF
  • 5. Time taken to disburse funds requested by the government for an eligible emergencyValeur20.000.800.00
    Date13 janvier 201728 février 2022
    Observation
  • 2. Value of production generated by the farmer subsidy scheme programValeur0.0032500000.000.00
    Date1 avril 201228 février 2022
    Observation
  • 3. Increase in sales of the supported producer organizationsValeur0.00172.000.00
    Date1 avril 201228 février 2022
    Observation
  • 1. Key elements to strengthen institutional capacity of MARNDR implementedValeur0.0081.250.00
    Date1 avril 201231 mars 2022
    Observation
  • 4. Direct project beneficiariesValeur0.0078242.000.00
    Date1 avril 201228 février 2022
    Observation
  • Female beneficiariesValeur0.0041.000.00
    Date1 avril 201216 avril 2018
    Observation
  • Households affected by Hurricane Matthew that received support from the Crisis Response WindowValeur0.0027958.000.00
    Date13 janvier 201728 février 2022
    Observation
  • Of which beneficiaries in the Southern regionValeur7445.0050888.000.00
    Date13 janvier 201728 février 2022
    Observation

INDICATEURS DE RÉSULTATS INTERMÉDIAIRES

INDICATEURNIVEAU DE RÉFÉRENCE EN COURS OBJECTIF
  • 1.1 Central Building built and equippedValeur0.001.000.00
    Date1 avril 201231 mars 2022
    Observation
  • 2.1 Producers adopting improved agriculture technologies promoted by the Project.Valeur0.0078.000.00
    Date1 avril 201228 février 2022
    Observation
  • 4.1 Number of agricultural producers registered in the MARNDR registry.Valeur14000.00224905.000.00
    Date13 janvier 201728 février 2022
    Observation
  • 1.2 Number of client days of training linked to SPS provided to epidemiological volunteers and private veterinarians.Valeur0.0014560.000.00
    Date1 avril 201228 février 2022
    Observation
  • 2.2 Number of hectares restored or converted to agroforestry productions by the ProjectValeur0.006013.000.00
    Date13 janvier 201728 février 2022
    Observation
  • 2.3 Number of client days of extension services provided to producers, members of producer organizations, different than SPS training.Valeur0.0037552.000.00
    Date1 avril 201228 février 2022
    Observation
  • 1.3 Number of cattle identified by the Project and included in the information systemValeur0.00317364.00250000.00
    Date1 avril 201228 février 20221 avril 2012
    Observation
  • 2.4 Satisfaction rate of participants of the farmer field schools.Valeur0.0090.620.00
    Date1 avril 201228 février 2022
    Observation
  • 1.4a Number of Departments where market prices have been collected and disseminated through a user-friendly web-based systemValeur0.004.000.00
    Date1 avril 201228 février 20221 avril 2012
    Observation
  • 2.5 Percentage of producer organizations having an operational investment at least 12 months after its completion.Valeur0.0080.000.00
    Date1 avril 201228 février 2022
    Observation
  • 2.6 Percentage of sub-projects that are sensitive to a) gender; b) environment; or c) nutrition.Valeur0.0082.800.00
    Date1 avril 201228 février 2022
    Observation
  • 1.4b Number of Departments where producers have had access to market information by SMS, community radio and/or by publication at all DDA and BACs.Valeur0.003.000.00
    Date1 avril 201228 février 2022
    Observation
  • 1.5 Number of didactical material elaborated and diffused in the Project zone, classified by themes.Valeur0.0018.000.00
    Date1 avril 201228 février 2022
    Observation
  • Area provided with new/improved irrigation or drainage servicesValeur0.002244.002000.00
    Date13 janvier 201728 février 202213 janvier 2017
    Observation
  • 1.6 Agricultural Middle School's infrastructure is upgradedValeurNoNo
    Date1 avril 201228 février 2022
    Observation