Rio Grande do Norte: Regional Development and Governance

Résumé*

The objective of the Rio Grande do Norte Regional Development and Governance Project for Brazil is to support the borrower's efforts to: (i) increase food security and access to productive infrastructure and markets for family agriculture; (ii) improve the quality of, and access to, health, education and public security services; and (iii) improve systems for public expenditure, human resource and physical asset management in the context of a results-based...

* Le résumé de projet étant tiré du document d'évaluation de projet (PAD), du rapport d'évaluation (SAR) ou du document du programme (PGD), il peut ne pas refléter exactement la teneur du projet en son état actuel.

Voir plus

Objectif de développement

The objective of the Project is to support the Borrower’s efforts to: (i) increase food security, access to productive infrastructure and markets for family agriculture; (ii) improve the quality of, and access to, health, education and public security services; and (iii) improve systems for public expenditure, human resource and physical asset management in the context of a results-based management approach.

Clé Détails

Projet Détails

  • P126452

  • Closed

  • Leonardo Bichara Rocha , Eirivelthon Santos Lima

  • Secretariat of Planning and Finance

  • Brésil

  • 18 avril 2012

  • (à la date de présentation au Conseil)

    25 juin 2013

  • 29 octobre 2013

  • USD 360.00 millions

  • B

  • 15 mai 2024

  • 31 décembre 2023

  • Yes

  • BANK APPROVED

  • Notes

Finances

Plan De Financement (Millions De Dollars)

Pas de données disponibles.
Org. De Financement Engagements
Borrower/Recipient 40.00
International Bank for Reconstruction and Development 360.00

Financement total du projet (USD millions)

Type de produit/service BIRD/IDA
Engagement BIRD 360.00
Engagement IDA N/D
Engagement BIRD + IDA 360.00
Instrument de prêt
Élément don N/D
Coût total du projet** 400.00

État récapitulatif du financement de la Banque (USD millions) au 31 mars 2025

Télécharger:
Pas de données disponibles.
Org. De Financement Date D'approbation Date De Cloture Montant En Principal Décaissé Remboursements Intérêts, Charges Et Commissions Financières

Activité financière détaillée au 31 mars 2025

Télécharger:
Pas de données disponibles.
Période Org. De Financement Type De Transaction Montant (USD)

Footnotes

Ratings

EXÉCUTION DU PROJET

Name Review Date
Financial Management Satisfactory 2023-10-26
Counterpart Funding Satisfactory 2023-10-26
Overall Implementation Progress (IP) Satisfactory 2023-10-26
Progress towards achievement of PDO Moderately Satisfactory 2023-10-26
Procurement Satisfactory 2023-10-26
Project Management Satisfactory 2023-10-26
Monitoring and Evaluation Moderately Satisfactory 2023-10-26

FIN D’EXÉCUTION DU PROJET

Pas de données disponibles.

NOTATION DE L’ÉVALUATION INDÉPENDANTE

Pas de données disponibles.

Cadre de résultats

INDICATEURS DES OBJECTIFS DE DÉVELOPPEMENT DU PROJET

INDICATEURNIVEAU DE RÉFÉRENCE EN COURS OBJECTIF
  • People benefited by subprojects promoting food securityValeur0.0056.000.00
    Date14 janvier 201329 décembre 2023
    Observation
  • Regional socioeconomic infrastructure implementedValeur0.0099.0050.00
    Date14 janvier 201329 décembre 202329 décembre 2023
    Observation
  • Provision of health services related to prioritized health care networks at the regional level (maternal and infant, urgency and emergency, and oncological health care networks)Valeur76.6475.6284.00
    Date14 janvier 20138 octobre 202130 décembre 2022
    Observation
  • Decrease in dropout rates of the state's secondary schools benefiting from the projectValeur12.3012.500.00
    Date14 janvier 201329 décembre 2023
    Observation
  • Systems improved and operationalValeur0.002.000.00
    Date14 janvier 201329 décembre 2023
    Observation
  • People assisted locally (municipal level) by preventive public security activities financed by the projectValeur40.0079.000.00
    Date10 mai 201929 décembre 2023
    Observation
  • Productive Investiments for market access with sanitary complianceValeur5.0070.0060.00
    Date23 décembre 201629 décembre 202331 mars 2021
    Observation
  • Direct project beneficiariesValeur0.00105681.00100000.00
    Date14 janvier 201329 décembre 202331 mars 2021
    Observation
  • Female beneficiariesValeur0.0020.000.00
    Date14 janvier 20136 avril 2018
    Observation

INDICATEURS DE RÉSULTATS INTERMÉDIAIRES

INDICATEURNIVEAU DE RÉFÉRENCE EN COURS OBJECTIF
  • Proportion of women whose births were performed in the region where they live, in relation to the total number of births performed in the state.Valeur71.9866.850.00
    Date14 janvier 201329 décembre 2023
    Observation
  • Number of people in rural areas provided with access to Improved Water Sources under the projectValeur0.0015837.0015300.00
    Date14 janvier 201329 décembre 202331 mai 2019
    Observation
  • Percentage of priority macroprocesses refurbished in the priority Government Institutions of the Project.Valeur0.00100.0060.00
    Date14 janvier 201329 décembre 202329 décembre 2023
    Observation
  • Proportion of hospitalizations due to clinical complications during gestation and post-partum, in relation to total hospitalizationfor obstetric procedures.Valeur13.2620.0611.50
    Date14 janvier 201329 décembre 202329 décembre 2023
    Observation
  • Community organizations with fee collection arrangements for the management and maintenance of the water supply subprojects financed by the project.Valeur0.0095.000.00
    Date14 janvier 201329 décembre 2023
    Observation
  • Percentage of critical audit recommendations implementedValeur0.0059.000.00
    Date14 janvier 201329 décembre 2023
    Observation
  • Reference center for the early detection of cancer, renovated, equipped and operational.Valeur0.002.000.00
    Date14 janvier 201329 décembre 2023
    Observation
  • Productive and socio-environmental investment organizations/groups led by womenValeur0.0047.0035.00
    Date14 janvier 20138 octobre 202131 mars 2021
    Observation
  • Regularized properties surveyed and registered in the Computerized SystemValeur0.0076.0070.00
    Date14 janvier 201329 décembre 202329 décembre 2023
    Observation
  • Proportion of biopsies done after the cervical cancer screening - pap smear.Valeur0.570.912.15
    Date14 janvier 201329 décembre 202331 mars 2021
    Observation
  • Extension of State roads improved by the projectValeur0.00274.000.00
    Date14 janvier 201329 décembre 2023
    Observation
  • Proportion of biopsies done after mammographyValeur0.560.915.00
    Date14 janvier 20138 octobre 202131 mars 2021
    Observation
  • Tourism and Cultural Infrastructure created / improved by the projectValeur0.0018.000.00
    Date14 janvier 201329 décembre 2023
    Observation
  • Hospital Emergency rooms renovated, equipped, and concluded by the project.Valeur0.006.000.00
    Date14 janvier 201329 décembre 2023
    Observation
  • State coverage of Cytopathology exams in women aged 25-64 yearsValeur0.380.260.44
    Date31 décembre 201929 décembre 202329 décembre 2023
    Observation
  • State coverage of mammography exams in women aged 50-69 yearsValeur0.280.210.50
    Date31 décembre 201929 décembre 202330 décembre 2022
    Observation
  • Guidelines and curricular matrices disseminated in state schoolsValeur0.0089.0060.00
    Date14 janvier 201329 décembre 202330 décembre 2022
    Observation
  • Schools of Pedagogical Innovation Projects (PIP) that have satisfactorily implemented subprojects.Valeur0.0084.0090.00
    Date14 janvier 201329 décembre 202329 décembre 2023
    Observation
  • Schools with computer labs with adequate useValeur0.0076.0070.00
    Date14 janvier 201329 décembre 202329 décembre 2023
    Observation
  • Schools (constructed, reformed and / or expanded) financed by the Project, meeting the main requirements of minimum operational physical standards (non-cumulative goals).Valeur0.0098.6070.00
    Date14 janvier 201329 décembre 202330 décembre 2022
    Observation
  • Productive investments supported by the project adopting sustainable social, crop production, and/or environmental practicesValeur0.0090.000.00
    Date8 février 201329 décembre 2023
    Observation
  • Number of secretariats with second level contractingValeur0.005.005.00
    Date14 janvier 201329 décembre 202329 décembre 2023
    Observation