Second Kerala Rural Water Supply and Sanitation Project (Jalanidhi II)

Résumé*

The development objective of the Second Kerala Rural Water Supply and Sanitation Project (Jalanidhi II) for India is to increase the access of rural communities to improved and sustainable water supply and sanitation services in Kerala, using a decentralized, demand-responsive approach. There are three components to the project. The first component of the project is institution building. This component will: (i) support capacity building of sector...

* Le résumé de projet étant tiré du document d'évaluation de projet (PAD), du rapport d'évaluation (SAR) ou du document du programme (PGD), il peut ne pas refléter exactement la teneur du projet en son état actuel.

Voir plus

Objectif de développement

The development objective of the proposed project is to increase the access of rural communities to improved and sustainable water supply and sanitation services in Kerala, using a decentralized, demand-responsive approach.

Clé Détails

Projet Détails

  • P121774

  • Closed

  • Srinivasa Podipireddy

  • Republic of India

  • Inde

  • 27 octobre 2010

  • (à la date de présentation au Conseil)

    15 décembre 2011

  • 17 avril 2012

  • USD 241.20 millions

  • KRWSA

  • Asie du Sud

  • 2012

  • USD 155.30 millions

  • B

  • 11 juillet 2024

  • 28 juin 2019

  • BANK APPROVED

  • Notes

Finances

Plan De Financement (Millions De Dollars)

Pas de données disponibles.
Org. De Financement Engagements
Local Govts. (Prov., District, City) of Borrowing Country 39.70
IDA Credit 155.30
Borrower/Recipient 46.20

Financement total du projet (USD millions)

Type de produit/service BIRD/IDA
Engagement BIRD N/D
Engagement IDA 155.30
Engagement BIRD + IDA 155.30
Instrument de prêt
Élément don N/D
Coût total du projet** 241.20

État récapitulatif du financement de la Banque (USD millions) au 31 mars 2025

Télécharger:
Pas de données disponibles.
Org. De Financement Date D'approbation Date De Cloture Montant En Principal Décaissé Remboursements Intérêts, Charges Et Commissions Financières

Activité financière détaillée au 31 mars 2025

Télécharger:
Pas de données disponibles.
Période Org. De Financement Type De Transaction Montant (USD)

Footnotes

Ratings

EXÉCUTION DU PROJET

Name Review Date
Procurement Moderately Satisfactory 2019-05-19
Project Management Satisfactory 2019-05-19
Counterpart Funding Satisfactory 2019-05-19
Monitoring and Evaluation Satisfactory 2019-05-19
Overall Implementation Progress (IP) Moderately Satisfactory 2019-05-19
Progress towards achievement of PDO Moderately Satisfactory 2019-05-19
Financial Management Satisfactory 2019-05-19

FIN D’EXÉCUTION DU PROJET

INDICATEURBILAN DE FIN D’EXÉCUTION ET DE RÉSULTATS: 12-20-2019
RésultatsModerately Satisfactory
Risques pour les résultats de développement
Performance de la BanqueModerately Satisfactory
Performance de l'emprunteur
Performance de l’État
Organisme d'exécution

NOTATION DE L’ÉVALUATION INDÉPENDANTE

INDICATEUREXAMEN RFE: 06-16-2020RAPPORT D’ÉVALUATION RÉTROSPECTIVE DE PROJET:
Évaluation Des RésultatsModerately Satisfactory N/a
Risques Pour Les Résultats De DéveloppementN/a
Performance De La BanqueModerately SatisfactoryN/a
Performance De L'emprunteurN/a
Performance De L’étatNot RatedN/a
Organisme D'exécutionN/a
Qualité Des RfeSubstantialN/a
Qualité Du Suivi-évaluationSubstantialN/a

Cadre de résultats

INDICATEURS DES OBJECTIFS DE DÉVELOPPEMENT DU PROJET

INDICATEURNIVEAU DE RÉFÉRENCE EN COURS OBJECTIF
  • Direct project beneficiariesValeur0.001547000.001746000.00
    Date1 janvier 201228 juin 201928 juin 2019
    Observation
  • Number of people in rural areas provided with access to Improved Water Sources under the projectValeur0.001157000.001376000.00
    Date1 janvier 201228 juin 201928 juin 2019
    Observation
  • People provided with access to "improved sanitation facilities” under the proj.Valeur0.00390000.00370000.00
    Date1 janvier 201228 juin 201928 juin 2019
    Observation
  • Number of project supported water supply schemes that are managed by beneficiary groups following demand responsive approachValeur0.002167.002175.00
    Date1 janvier 201228 juin 201928 juin 2019
    Observation
  • Number of water supply schemes improved under the project that are delivering satisfactory services to all intended households by recovering full operational costsValeur0.002030.001950.00
    Date1 janvier 201228 juin 201928 juin 2019
    Observation
  • Female beneficiariesValeur0.0050.230.00
    Date1 janvier 201215 mars 2018
    Observation
  • People provided with access to “improved sanitation facilities”- ruralValeur0.00390000.00370000.00
    Date1 janvier 201228 juin 201928 juin 2019
    Observation

INDICATEURS DE RÉSULTATS INTERMÉDIAIRES

INDICATEURNIVEAU DE RÉFÉRENCE EN COURS OBJECTIF
  • People trained to improve hygiene behavior/sanitation practices under the projValeur0.0072752.0056700.00
    Date31 janvier 201228 juin 201928 juin 2019
    Observation
  • Number of project supported multi-Gram Panchayat schemes by local institutions successfully demonstrated improved service deliveryValeur0.003.005.00
    Date1 janvier 201228 juin 201928 juin 2019
    Observation
  • Improved latrines constructed under the projectValeur0.0036376.0010000.00
    Date1 janvier 201228 juin 201928 juin 2019
    Observation
  • Number of capacity building traning events carried out (cumulative)Valeur0.008546.009120.00
    Date1 janvier 201228 juin 201928 juin 2019
    Observation
  • Piped household water connections that are benefiting from rehabilitation works undertaken by the projectValeur0.00102893.00112370.00
    Date1 janvier 201228 juin 201928 juin 2019
    Observation
  • People trained to improve hygiene behavior/sanitation practices - femaleValeur15684.0036376.0030000.00
    Date31 mars 200928 juin 201928 juin 2019
    Observation
  • Number of project GPs benefiting from technical assistance and capacity building (cumulative)Valeur0.00598.00300.00
    Date1 janvier 201222 mars 201928 juin 2019
    Observation
  • No of person days of capacity building carried outValeur0.00622434.000.00
    Date1 janvier 20127 mars 2017
    Observation
  • Piped household water connections that are benifitting from new water schemes underValeur0.000.000.00
    Date1 janvier 2012
    Observation
  • Number of water utilities that the project is supportingValeur0.001.001.00
    Date1 janvier 201228 juin 201928 juin 2019
    Observation
  • Number of GPs where interventions for safe disposal of solid and liquid waste successfully implemented and managed on a pilot basisValeur0.000.0010.00
    Date1 janvier 201222 mars 201928 juin 2019
    Observation
  • Number of sector development studies successfully completed (cumulative)Valeur0.0010.009.00
    Date1 janvier 201228 juin 201928 juin 2019
    Observation
  • Total number of new water supply schemes being operated (cumulative)Valeur0.001700.001775.00
    Date1 janvier 201228 juin 201928 juin 2019
    Observation
  • Total Number of Rehabilitated Water Supply schemes being operatedValeur0.000.000.00
    Date1 janvier 2012
    Observation
  • Number of other water service providers that the project is supportingValeur0.003578.004713.00
    Date1 janvier 201228 juin 201928 juin 2019
    Observation