MA-Solid Waste Sector DPL2

Résumé*

The development objective of the Development Policy Loan (DPL) program is to support the Government of Morocco (GoM) in implementing its program of reforms aimed at improving the financial, environmental and social performance of the municipal solid waste sector in Morocco. The first DPL supported the key foundations of the Government's reform program, which established the enabling environment for an integrated and affordable municipal solid waste...

* Le résumé de projet étant tiré du document d'évaluation de projet (PAD), du rapport d'évaluation (SAR) ou du document du programme (PGD), il peut ne pas refléter exactement la teneur du projet en son état actuel.

Voir plus

Objectif de développement

The objective is to support the government in implementing its program for the reform of the municipal solid waste sector in Morocco through: (i) enhancing the governance of the sector; (ii) improving the sustainability of municipal solid waste services; and (iii) mainstreaming environmental and social dimensions.

Clé Détails

Projet Détails

  • P119781

  • Closed

  • Jaafar Sadok Friaa

  • N/A

  • Maroc

  • 20 mai 2010

  • (à la date de présentation au Conseil)

    20 décembre 2010

  • 18 mai 2011

  • USD 138.60 millions

  • N/A

  • 15 janvier 2013

  • 31 décembre 2011

  • BANK APPROVED

  • P104937

  • Notes

Finances

Plan De Financement (Millions De Dollars)

Pas de données disponibles.
Org. De Financement Engagements
International Bank for Reconstruction and Development 138.60

Financement total du projet (USD millions)

Type de produit/service BIRD/IDA
Engagement BIRD 138.60
Engagement IDA N/D
Engagement BIRD + IDA 138.60
Instrument de prêt
Élément don N/D
Coût total du projet** 138.60

État récapitulatif du financement de la Banque (USD millions) au 31 mars 2025

Télécharger:
Pas de données disponibles.
Org. De Financement Date D'approbation Date De Cloture Montant En Principal Décaissé Remboursements Intérêts, Charges Et Commissions Financières

Activité financière détaillée au 31 mars 2025

Télécharger:
Pas de données disponibles.
Période Org. De Financement Type De Transaction Montant (USD)

Footnotes

Ratings

EXÉCUTION DU PROJET

Name Review Date
Progress towards achievement of PDO Satisfactory 2011-02-21
Monitoring and Evaluation Satisfactory 2011-02-21
Overall Implementation Progress (IP) Satisfactory 2011-02-21
Program Management Satisfactory 2011-02-21

FIN D’EXÉCUTION DU PROJET

INDICATEURBILAN DE FIN D’EXÉCUTION ET DE RÉSULTATS: 06-26-2012
RésultatsSubstantial
Risques pour les résultats de développementModest
Performance de la BanqueSubstantial
Performance de l'emprunteurSubstantial
Performance de l’ÉtatSubstantial
Organisme d'exécutionSubstantial

NOTATION DE L’ÉVALUATION INDÉPENDANTE

INDICATEUREXAMEN RFE: 12-14-2021RAPPORT D’ÉVALUATION RÉTROSPECTIVE DE PROJET: 12-11-2013
Évaluation Des RésultatsModerately Satisfactory Moderately Satisfactory
Risques Pour Les Résultats De DéveloppementSignificantModerate
Performance De La BanqueSatisfactorySatisfactory
Performance De L'emprunteurSatisfactorySatisfactory
Performance De L’étatSatisfactory
Organisme D'exécutionSatisfactory
Qualité Des RfeSatisfactory
Qualité Du Suivi-évaluationModest

Cadre de résultats

INDICATEURS DES OBJECTIFS DE DÉVELOPPEMENT DU PROJET

INDICATEURNIVEAU DE RÉFÉRENCE EN COURS OBJECTIF

INDICATEURS DE RÉSULTATS INTERMÉDIAIRES

INDICATEURNIVEAU DE RÉFÉRENCE EN COURS OBJECTIF
  • Annual costed -workplans and progress reports are systematically reviewed and adopted by the CN-PNDM.Valeur03 progress reports and 2 annual programs6 progress reports and 3 annual programs
    Date30 décembre 200830 novembre 201030 mai 2012
    Observation
  • Percentage of total government financial support under the PNDM allocated based on the adopted eligibility criteria.Valeur0.0050.00100.00
    Date30 décembre 200830 novembre 201030 mai 2012
    Observation
  • Solid waste infrastructure supported through the PNDM is consistent with national regulations, based on reviews of projects (to be verified by project sampling in Q3 FY12).Valeur0.000.00100.00
    Date30 décembre 200830 novembre 201030 mai 2012
    Observation
  • Increased competition in tenders for MSWM, as measured by the increase in number of received bids between 2008 and 2011, reported at bid opening records.Valeur4 to 5 bids per tenderSignificant improvement in term of bidder particip
    Date30 décembre 200830 novembre 201030 mai 2012
    Observation
  • Number of thematic conventions signed between local governments and the State targeting the upgrade of MSWMValeur0.003.0010.00
    Date30 décembre 200830 novembre 201030 mai 2012
    Observation
  • Change in the perception by the urban population of MSWM as a priority area of intervention, as measured by sample survey.ValeurN/AN/A
    Date
    Observation
  • Improved coverage of the costs of SWM services in municipalities supported by the PNDM.Valeur172840000.000.00370000000.00
    Date30 décembre 2011
    Observation
  • Number of local governments benefitting from capacity-building activitiesValeur0.000.000.00
    Date30 décembre 2008
    Observation
  • Number of EIAs related to solid waste investments reviewed and approved by regional or national EIA committeesValeur0.0017.000.00
    Date
    Observation
  • Percentage of collected waste disposed in sanitary landfills by 2012Valeur0.0028.0030.00
    Date30 novembre 201030 mai 2012
    Observation
  • Number of open dumpsites closed/ rehabilitated by 2012Valeur4.000.000.00
    Date30 novembre 2010
    Observation
  • Number of wastepickers benefiting from social inclusion initiativesValeur0.000.00100.00
    Date30 mai 2012
    Observation