Org. De Financement | Engagements |
---|---|
IDA Grant | 40.00 |
P117103
Closed
Naila Ahmed
Islamic Republic of Afghanistan
19 mai 2010
(à la date de présentation au Conseil)
29 juin 2010
6 octobre 2010
USD 40.00 millions
Ministry of Rural Rehabilitation & Development
2010
USD 40.00 millions
B
1 mai 2024
31 mars 2017
BANK APPROVED
Org. De Financement | Engagements |
---|---|
IDA Grant | 40.00 |
Type de produit/service | BIRD/IDA |
---|---|
Engagement BIRD | N/D |
Engagement IDA | 40.00 |
Engagement BIRD + IDA | 40.00 |
Instrument de prêt | |
---|---|
Élément don | N/D |
Coût total du projet** | 40.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2017-03-30 |
Project Management | Satisfactory | 2017-03-30 |
Financial Management | Satisfactory | 2017-03-30 |
Monitoring and Evaluation | Satisfactory | 2017-03-30 |
Overall Implementation Progress (IP) | Satisfactory | 2017-03-30 |
Procurement | Satisfactory | 2017-03-30 |
INDICATEUR | BILAN DE FIN D’EXÉCUTION ET DE RÉSULTATS: 12-27-2017 |
---|---|
Résultats | Substantial |
Risques pour les résultats de développement | |
Performance de la Banque | Substantial |
Performance de l'emprunteur | |
Performance de l’État | |
Organisme d'exécution |
INDICATEUR | EXAMEN RFE: 10-28-2018 | RAPPORT D’ÉVALUATION RÉTROSPECTIVE DE PROJET: |
---|---|---|
Évaluation Des Résultats | Satisfactory | N/a |
Risques Pour Les Résultats De Développement | N/a | |
Performance De La Banque | Moderately Satisfactory | N/a |
Performance De L'emprunteur | N/a | |
Performance De L’état | Not Rated | N/a |
Organisme D'exécution | N/a | |
Qualité Des Rfe | Substantial | N/a |
Qualité Du Suivi-évaluation | Substantial | N/a |
INDICATEUR | NIVEAU DE RÉFÉRENCE | EN COURS | OBJECTIF |
---|
Min. of 70% of sampled communities recognize CDCs as the legitimate institution and representative of communities | Valeur | 0 | 70% | 96% (14,251) of sampled communities, recognize the |
Date | 10 juin 2010 | 10 juin 2010 | 31 mars 2017 | |
Observation |
Minimum of 60% of CDCs perform their functional mandates in the areas of community development and coordination, project implementation and conflict resolution | Valeur | 0 | 60% | Out of 4,733 monitored CDCs, 80% (3,802) CDCs perf |
Date | 10 juin 2010 | 10 juin 2010 | 31 mars 2017 | |
Observation |
Minimum of 70% of sampled communities have improved access to services. | Valeur | 0 | 80% (6,107) of the sampled communities have access | |
Date | 10 juin 2010 | 20 novembre 2015 | 31 mars 2017 | |
Observation |
At least 50% of total beneficiaries are female | Valeur | 0 | 50% | 48% (13,764,525) of NSP III total beneficiaries (2 |
Date | 10 juin 2010 | 10 juin 2010 | 31 mars 2017 | |
Observation |
Minimum of 70% of sampled women representatives in the CDCs take active part in decision making related to community development | Valeur | 0.00 | 70.00 | 79.00 |
Date | 10 juin 2010 | 10 juin 2010 | 31 mars 2017 | |
Observation |
INDICATEUR | NIVEAU DE RÉFÉRENCE | EN COURS | OBJECTIF |
---|
Minimum of 80% of CDCs have new elections for leadership through democratic elections and secret ballot at the appropriate time. | Valeur | 0 | 80% | Out of the total (15,904) mobilized communities, t |
Date | 30 septembre 2011 | 10 juin 2010 | 31 mars 2017 | |
Observation |
90% of CDCs have been trained on core and second phase training topics | Valeur | 0 | 90% | 99% (26,282) of elected CDCs trained as per NSP OM |
Date | 10 juin 2010 | 10 juin 2010 | 31 mars 2017 | |
Observation |
Minimum of 30% of sampled CDCs attempt to form linkages with government and non-government actors. | Valeur | 0 | 30% | 71% (2,622) CDCs formed linkages with government a |
Date | 10 juin 2010 | 10 juin 2010 | 31 mars 2017 | |
Observation |
35% of CDC members nationally are women | Valeur | 38% under NSP I and II | 35% | Out of the total number of CDC members (158,228) i |
Date | 10 juin 2010 | 10 juin 2010 | 31 mars 2017 | |
Observation |
70% of sampled communities satisfied with FP performance | Valeur | 0 | 70% | 96% (6,913) of CDCs are satisfied with performance |
Date | 10 juin 2010 | 10 juin 2010 | 31 mars 2017 | |
Observation |
Min. of 80% of new CDCs complete their CDPs according to NSP principles and operational guidelines (First block grant communities) | Valeur | 0 | 80% | 99.6% (12,250) out of (12,287) new CDCs completed |
Date | 10 juin 2010 | 10 juin 2010 | 31 mars 2017 | |
Observation |
At least one subproject completed by 80% of CDCs (First block grant communities) | Valeur | 0 | 80% | Out of total 11,760 CDCs financed, 98% (11,557) of |
Date | 10 juin 2010 | 10 juin 2010 | 31 mars 2017 | |
Observation |
Min. of 70% of sampled infrastructure subprojects are functional and used by communities one year after completion (First block grant communities) | Valeur | 0 | 70% | 93% (7,208) of 7,710 infrastructure completed sub |
Date | 10 juin 2010 | 10 juin 2010 | 31 mars 2017 | |
Observation |
Of the eligible CDCs, min. of 70% of CDPs revised and completed according to NSP principles and operation guidelines (Repeater block grant communities) | Valeur | 0 | 70% | Out of 11,505 CDCs re-elected 99.9% (11,498) of CD |
Date | 10 juin 2010 | 10 juin 2010 | 31 mars 2017 | |
Observation |
At least one subproject completed by 70% of eligible CDCs (Repeater block grant communities) | Valeur | 0 | 70% | Out of total 11,409 CDCs financed, 99% (11,343) of |
Date | 10 juin 2010 | 10 juin 2010 | 31 mars 2017 | |
Observation |
Min. of 75% of sampled infrastructure subprojects are functional and used by communities one year after completion | Valeur | For NSP I & II 85% of sampled sub-projects were fu | 75% | Out of the total 7,331 Sub-Projects monitored 80% |
Date | 10 juin 2010 | 10 juin 2010 | 31 mars 2017 | |
Observation |
Min. of 70% of sampled CDCs conduct social audit meetings | Valeur | Social audit meetings were added as an enhanced fe | 70% | Out of 13,817 communities monitored, 20% (2,822) o |
Date | 10 juin 2010 | 10 juin 2010 | 31 mars 2017 | |
Observation |
80% of complaints processed by NSP using agreed service standards | Valeur | 0 | 80% | Out of 2,273 grievances received, 2,009 (88%) have |
Date | 10 juin 2010 | 10 juin 2010 | 31 mars 2017 | |
Observation |
One annual NSP progress report produced | Valeur | 0 | 5 | 0 |
Date | 10 juin 2010 | 10 juin 2010 | 31 mars 2017 | |
Observation |
90% of FP invoices paid in accordance with contractual timetable | Valeur | 75% | 90% | 76% of FP invoices are paid in accordance with con |
Date | 10 juin 2010 | 10 juin 2010 | 31 mars 2017 | |
Observation |
Number of additional classrooms built or rehabilitated at the primary level resulting from project interventions. | Valeur | 0.00 | 0.00 | 2995.00 |
Date | 10 juin 2010 | 1 septembre 2013 | 31 mars 2017 | |
Observation |
Community contribution in the total project costs (percentage) | Valeur | 0.00 | 10.00 | 12.00 |
Date | 10 juin 2010 | 10 juin 2010 | 31 mars 2017 | |
Observation |
Roads constructed, Rural | Valeur | 0.00 | 0.00 | 12493.00 |
Date | 10 juin 2010 | 1 septembre 2013 | 31 mars 2017 | |
Observation |
Roads rehabilitated, Rural | Valeur | 0.00 | 0.00 | 141.00 |
Date | 10 juin 2010 | 1 septembre 2013 | 31 mars 2017 | |
Observation |
Number of people in rural areas provided with access to Improved Water Sources under the project | Valeur | 0.00 | 0.00 | 5056937.00 |
Date | 10 juin 2010 | 1 septembre 2013 | 31 mars 2017 | |
Observation |
Improved community water points constructed or rehabilitated under the project | Valeur | 0.00 | 0.00 | 39449.00 |
Date | 10 juin 2010 | 1 septembre 2013 | 31 mars 2017 | |
Observation |
Improved latrines constructed under the project | Valeur | 0.00 | 0.00 | 7953.00 |
Date | 10 juin 2010 | 1 septembre 2013 | 31 mars 2017 | |
Observation |
Area provided with irrigation and drainage services (ha) | Valeur | 0.00 | 0.00 | 361523.00 |
Date | 10 juin 2010 | 1 septembre 2013 | 31 mars 2017 | |
Observation |
Number of CDCs received maintenance cash grants | Valeur | 0.00 | 0.00 | 10914.00 |
Date | 26 novembre 2015 | 26 novembre 2015 | 31 mars 2017 | |
Observation |
Min. of 60% of eligible CDCs have Community Participatory Monitoring (CPM) teams functioning | Valeur | 0 | 60% | 95% of eligible CDCs under NSP III have CPM teams |
Date | 10 juin 2010 | 10 juin 2010 | 31 mars 2017 | |
Observation |
50% of CDCs solved the confilicts raised at their own communities | Valeur | 0 | 50% | In total of 4,679 CDCs 4,938 Conflicts were raised |
Date | 10 juin 2010 | 10 juin 2010 | 31 mars 2017 | |
Observation |
Number of NSP’s staff trained (male and female) | Valeur | 0 | 0 | In total 5,268 NSP staff (4,826 male and 442 femal |
Date | 10 juin 2010 | 10 juin 2010 | 31 mars 2017 | |
Observation |
Number of CDC members (male and female) trained | Valeur | 0 | 0 | As a result of mentioned training hours, in total |
Date | 10 juin 2010 | 10 juin 2010 | 31 mars 2017 | |
Observation |
Total community contribution (US$) | Valeur | 0.00 | 0.00 | 106615673.00 |
Date | 10 juin 2010 | 10 juin 2010 | 31 mars 2017 | |
Observation |
Area provided with irrigation and drainage services - New (ha) | Valeur | 0.00 | 0.00 | 338310.00 |
Date | 10 juin 2010 | 1 septembre 2013 | 31 mars 2017 | |
Observation |
Area provided with irrigation and drainage services - Improved (ha) | Valeur | 0.00 | 0.00 | 23213.00 |
Date | 10 juin 2010 | 1 septembre 2013 | 31 mars 2017 | |
Observation |