Org. De Financement | Engagements |
---|---|
IDA Credit | 132.00 |
Borrower/Recipient | 199.00 |
Development Bank of the Central African States | 15.00 |
African Development Bank | 29.00 |
EC: European Investment Bank | 40.00 |
FRANCE: French Agency for Development | 79.00 |
P114077
Closed
Nicolas Sans
Electricity Development Corporation (EDC)
4 décembre 2009
(à la date de présentation au Conseil)
27 mars 2012
19 mars 2013
USD 494.00 millions
Electricity Development Corporation (EDC)
2012
USD 295.00 millions
A
14 mai 2024
28 juin 2019
BANK APPROVED
Org. De Financement | Engagements |
---|---|
IDA Credit | 132.00 |
Borrower/Recipient | 199.00 |
Development Bank of the Central African States | 15.00 |
African Development Bank | 29.00 |
EC: European Investment Bank | 40.00 |
FRANCE: French Agency for Development | 79.00 |
Type de produit/service | BIRD/IDA |
---|---|
Engagement BIRD | N/D |
Engagement IDA | 132.00 |
Engagement BIRD + IDA | 132.00 |
Instrument de prêt | |
---|---|
Élément don | 163.00 |
Coût total du projet** | 494.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2019-03-12 |
Financial Management | Moderately Satisfactory | 2019-03-12 |
Procurement | Satisfactory | 2019-03-12 |
Project Management | Moderately Satisfactory | 2019-03-12 |
Counterpart Funding | Satisfactory | 2019-03-12 |
Monitoring and Evaluation | Satisfactory | 2019-03-12 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2019-03-12 |
INDICATEUR | BILAN DE FIN D’EXÉCUTION ET DE RÉSULTATS: 12-28-2019 |
---|---|
Résultats | Substantial |
Risques pour les résultats de développement | |
Performance de la Banque | Substantial |
Performance de l'emprunteur | |
Performance de l’État | |
Organisme d'exécution |
INDICATEUR | EXAMEN RFE: 06-19-2020 | RAPPORT D’ÉVALUATION RÉTROSPECTIVE DE PROJET: |
---|---|---|
Évaluation Des Résultats | Satisfactory | N/a |
Risques Pour Les Résultats De Développement | N/a | |
Performance De La Banque | Satisfactory | N/a |
Performance De L'emprunteur | N/a | |
Performance De L’état | N/a | |
Organisme D'exécution | N/a | |
Qualité Des Rfe | Substantial | N/a |
Qualité Du Suivi-évaluation | Substantial | N/a |
INDICATEUR | NIVEAU DE RÉFÉRENCE | EN COURS | OBJECTIF |
---|
Generation Capacity of Hydropower rehabilitated under the project | Valeur | 0.00 | 120.00 | 0.00 |
Date | 2 août 2013 | 28 juin 2019 | ||
Observation |
People provided with access to electricity by hhold connections-Grid | Valeur | 0.00 | 2400.00 | 0.00 |
Date | 2 août 2013 | 28 juin 2019 | ||
Observation |
Quantity of hydroelectricity additionally generated under the project at the two existing plants on the Sanaga River | Valeur | 0.00 | 684.00 | 0.00 |
Date | 1 mars 2012 | 28 juin 2019 | ||
Observation |
Ppl provided wth elec. by hhold conn.–Offgrid/minigrid–Only renewable sources | Valeur | 0.00 | 2400.00 | 0.00 |
Date | 2 août 2013 | 28 juin 2019 | ||
Observation |
Quantity of hydroelectricity additionally generated under the project - New capacity at Lom Pangar | Valeur | 0.00 | 0.00 | 0.00 |
Date | 1 mars 2012 | 28 juin 2019 | ||
Observation |
Number of households newly connected to the electricity grid | Valeur | 0.00 | 0.00 | 0.00 |
Date | 1 mars 2012 | 28 juin 2019 | ||
Observation |
Direct project beneficiaries | Valeur | 0.00 | 5921860.00 | 0.00 |
Date | 1 mars 2012 | 28 juin 2019 | ||
Observation |
Female beneficiaries | Valeur | 50.60 | 50.60 | 0.00 |
Date | 1 mars 2012 | 18 mai 2018 | ||
Observation |
Generation Capacity of Hydropower constructed or rehabilitated under the project | Valeur | 0.00 | 120.00 | 120.00 |
Date | 2 août 2013 | 28 juin 2019 | 31 décembre 2018 | |
Observation |
Guaranteed all-season water flow of the Sanaga River. | Valeur | 720.00 | 1050.00 | 0.00 |
Date | 1 mars 2012 | 28 juin 2019 | ||
Observation |
People provided with access to electricity by household connections | Valeur | 0.00 | 2400.00 | 0.00 |
Date | 2 août 2013 | 28 juin 2019 | ||
Observation |
Generation Capacity of Hydropower constructed under the project | Valeur | 0.00 | 30.00 | 30.00 |
Date | 2 août 2013 | 28 juin 2019 | 28 juin 2019 | |
Observation |
Ppl pvd wth elec. by hhold conn.–Offgrid/minigrid–Any source except only renewable | Valeur | 0.00 | 2400.00 | 0.00 |
Date | 2 août 2013 | 28 juin 2019 | ||
Observation |
INDICATEUR | NIVEAU DE RÉFÉRENCE | EN COURS | OBJECTIF |
---|
Commissioning of Lom Pangar regulating dam completed | Valeur | No | Yes | |
Date | 1 mars 2012 | 28 juin 2019 | ||
Observation |
Transmission lines constructed or rehabilitated under the project | Valeur | 0.00 | 0.00 | 0.00 |
Date | 2 août 2013 | 28 juin 2019 | ||
Observation |
Gorilla population in Deng Deng Forest | Valeur | 300.00 | 300.00 | 0.00 |
Date | 31 décembre 2010 | 28 juin 2019 | ||
Observation |
Operation manual for the dam and reservoir is completed and staff are trained on its use | Valeur | No | Yes | |
Date | 1 mars 2012 | 28 juin 2019 | ||
Observation |
Dam Safety Panel recommendations are implemented in a timely and quality manner | Valeur | No | Yes | |
Date | 1 mars 2012 | 28 juin 2019 | ||
Observation |
Annual Expert Panel environmental and social monitoring report disseminated and made publically available | Valeur | No | Yes | |
Date | 1 mars 2012 | 28 juin 2019 | ||
Observation |
Average annual household income of project directly affected persons | Valeur | 1360.00 | 1440.00 | 0.00 |
Date | 1 mars 2012 | 28 juin 2019 | ||
Observation |
Transmission lines rehabilitated under the project | Valeur | 0.00 | 0.00 | 0.00 |
Date | 2 août 2013 | 28 juin 2019 | ||
Observation |
Transmission lines constructed under the project | Valeur | 0.00 | 0.00 | 0.00 |
Date | 2 août 2013 | 28 juin 2019 | ||
Observation |
Commissioning of Lom Pangar power plant completed | Valeur | No | No | |
Date | 1 mars 2012 | 28 juin 2019 | ||
Observation |
Transmission line constructed under the project | Valeur | 0.00 | 0.00 | 0.00 |
Date | 1 mars 2012 | 28 juin 2019 | ||
Observation |