Org. De Financement | Engagements |
---|---|
IDA Credit | 9.30 |
Borrower/Recipient | 1.00 |
P108768
Closed
Bryan Land
Ministry of Finance
14 mars 2008
(à la date de présentation au Conseil)
26 juin 2008
4 mai 2009
USD 10.30 millions
Ministry of Finance
2008
USD 9.30 millions
B
16 octobre 2023
31 décembre 2015
BANK APPROVED
Org. De Financement | Engagements |
---|---|
IDA Credit | 9.30 |
Borrower/Recipient | 1.00 |
Type de produit/service | BIRD/IDA |
---|---|
Engagement BIRD | N/D |
Engagement IDA | 9.30 |
Engagement BIRD + IDA | 9.30 |
Instrument de prêt | |
---|---|
Élément don | N/D |
Coût total du projet** | 10.30 |
Name | Review | Date |
---|---|---|
Overall Safeguards Rating | Moderately Satisfactory | 2016-06-03 |
Counterpart Funding | Satisfactory | 2016-06-03 |
Project Management | Satisfactory | 2016-06-03 |
Procurement | Satisfactory | 2016-06-03 |
Progress towards achievement of PDO | Moderately Satisfactory | 2016-06-03 |
Financial Management | Satisfactory | 2016-06-03 |
Monitoring and Evaluation | Satisfactory | 2016-06-03 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2016-06-03 |
Overall Safeguards Rating | Moderately Satisfactory | 2016-06-03 |
INDICATEUR | BILAN DE FIN D’EXÉCUTION ET DE RÉSULTATS: 03-31-2017 |
---|---|
Résultats | Moderately Unsatisfactory |
Risques pour les résultats de développement | Substantial |
Performance de la Banque | Moderately Satisfactory |
Performance de l'emprunteur | Moderately Satisfactory |
Performance de l’État | Moderately Satisfactory |
Organisme d'exécution | Substantial |
INDICATEUR | EXAMEN RFE: 12-22-2017 | RAPPORT D’ÉVALUATION RÉTROSPECTIVE DE PROJET: |
---|---|---|
Évaluation Des Résultats | Moderately Unsatisfactory | N/a |
Risques Pour Les Résultats De Développement | Substantial | N/a |
Performance De La Banque | Moderately Satisfactory | N/a |
Performance De L'emprunteur | Moderately Unsatisfactory | N/a |
Performance De L’état | Moderately Unsatisfactory | N/a |
Organisme D'exécution | Moderately Unsatisfactory | N/a |
Qualité Des Rfe | Substantial | N/a |
Qualité Du Suivi-évaluation | Modest | N/a |
INDICATEUR | NIVEAU DE RÉFÉRENCE | EN COURS | OBJECTIF |
---|
Annual Budget decisions to replenish or withdraw from newly established Sovereign Wealth Fund are made based on agreed Macroeconomic criteria | Valeur | None | Fully Achieved. Fiscal Stabiltiy Law adopted in 20 | Criteria agreed and implemented in Budget framewor |
Date | 26 juin 2009 | 23 mai 2016 | 31 décembre 2013 | |
Observation |
Level of mining related transfers from national government to Aimag and Soum authorities is known and publicly disclosed. | Valeur | Not currently disclosed | Fully achieved. Integrated Budget Law of Dec 2011 | Disclosed and discussed/monitored by citizen group |
Date | 26 juin 2009 | 23 mai 2016 | 31 décembre 2013 | |
Observation |
Mining Tax Audits are completed and assessments raised | Valeur | none currently | Fully Achieved. 2 audits completed; guidelines and | Minimum of two audits completed |
Date | 26 juin 2009 | 23 mai 2016 | 31 mars 2015 | |
Observation |
Clear authority and responsibilities for Government mining sector management institutions, especially regarding environmental and social aspects associated with mining activities. | Valeur | Roles confused resulting in gaps and conflicts | Fully Achieved. Functional management review of Mo | Institutional roles clarified in line with clearly |
Date | 26 juin 2009 | 23 mai 2016 | 31 mars 2015 | |
Observation |
mineral licensing procedures streamlined and processing times reduced | Valeur | 4-6 months | Fully Achieved. Mineral Licencing processing is co | 2 months |
Date | 26 juin 2009 | 23 mai 2016 | 31 mars 2015 | |
Observation |
Geological information is digitized and published and readily available in user friendly digital formats. | Valeur | very limited, no digital geochemistry | Target not met. MSISTAP financed an institutional | 200,000 data points digitised |
Date | 26 juin 2009 | 23 mai 2016 | 31 mars 2015 | |
Observation |
Companies and civil society participate in consultation for pieces of legislation and regulation for mining sector through public fora arranged by the government. | Valeur | No data availabe. | Fully achieved. Companies and Civil society partic | Consultations taking place for policy, each piece |
Date | 28 mars 2014 | 23 mai 2016 | 31 mars 2015 | |
Observation |
INDICATEUR | NIVEAU DE RÉFÉRENCE | EN COURS | OBJECTIF |
---|
Ministry of Mining policies reviewed and revised | Valeur | Some work has been undertaken to review the Minist | Fully Achieved. New Mineral Policy formally adopte | Government adopts recommendations in the form of p |
Date | 28 mars 2014 | 23 mai 2016 | 31 mars 2015 | |
Observation |
Modern company reporting requirements regulations are prepared, promulgated, implemented, and monitored | Valeur | Reporting exists in regulations but needs modifica | Almost achieved -Mining law updated in July 2014 a | regulations issues and passed |
Date | 28 mars 2014 | 23 mai 2016 | 31 mars 2015 | |
Observation |
Provision of management-related and governance related training events to build capabilities needed within Erdenes MGL. | Valeur | no systemic capacity building | Achieved | Management-related and governance related training |
Date | 28 mars 2014 | 23 mai 2016 | 31 mars 2015 | |
Observation |
Sovereign Wealth Fund or alternative revenue stabilisation mechanism established | Valeur | Mongolian Development Fund in place but deficient | Fully Achieved. Soverign Wealth Fund established i | New Fund Operational |
Date | 26 juin 2009 | 23 mai 2016 | 31 mars 2015 | |
Observation |
Preparation of Draft Model Mineral Development Agreement | Valeur | First draft prepared | Partially Achieved. Production Sharing Agreement d | Draft Model PSA and Mining Agreements consistent w |
Date | 26 juin 2009 | 23 mai 2016 | 31 décembre 2013 | |
Observation |
Support establishment of mechanisms for preparation and dissemination of independent professional mining sector economic and policyreports. | Valeur | No policy unit serving Prime Minister | Fully Achieved. Several reports produced by a rese | Produce first report |
Date | 26 juin 2009 | 23 mai 2016 | 31 mars 2015 | |
Observation |
Modern Mining cadastre regulation adopted and promulgated | Valeur | Regulations under preparation | Fully Achieved. Mining law revised in July 2014 wh | Mining Cadastre is in use and has public access an |
Date | 26 juin 2009 | 23 mai 2016 | 31 mars 2015 | |
Observation |
Income tax laws on mining amended and supporting regulations drafted | Valeur | Income tax law for mining deficient | Fully Achieved - Windfall profit tax law of 2006 r | Final modifications to tax laws submitted to Parli |
Date | 26 juin 2009 | 23 mai 2016 | 31 mars 2015 | |
Observation |
Options study prepared on double taxation treaties | Valeur | Treaties exist but Government dissatisfied with op | Fully Achieved | Work completed ondouble taxationtreaties –Gover |
Date | 26 juin 2009 | 23 mai 2016 | 31 décembre 2013 | |
Observation |
GDNT tax audit staff trained and competent to carry out mining company tax audits | Valeur | no staff trained to international standards | Fully Achieved; tax audit department received mult | 10 staff trained of which 2 are leading mining tax |
Date | 26 juin 2009 | 23 mai 2016 | 31 mars 2015 | |
Observation |
Modern occupation, health and safety regulations are prepared, promulgated, implemented and monitored. | Valeur | Regulations exist but require update and moderniza | Partially Achieved. Mining law adopted, regulation | Legislation passed, authorities actively monitorin |
Date | 28 mars 2014 | 23 mai 2016 | 31 mars 2015 | |
Observation |
Strategic environmental & social assessment undertaken, areas for improvement in social (including gender) & environmental regulation identified, recommendations made for updating laws | Valeur | Limited | Fully Achieved. SESA completed in December, 2014. | Results presented, Government responding to key fi |
Date | 28 mars 2014 | 23 mai 2016 | 31 mars 2015 | |
Observation |
Modern mine closure and post closure regulations are prepared and promulgated | Valeur | law and regulations require closure planning but n | Partially achieved -- TA provided (jointly with BG | Modern mine closure and post closure regulations a |
Date | 28 mars 2014 | 23 mai 2016 | 31 mars 2015 | |
Observation |
Erdenes MGL financial reports are provided quarterly to the Board of Directors. | Valeur | not systemic reporting | Fully Achieved | Financial reports are provided quarterly to the Bo |
Date | 28 mars 2014 | 23 mai 2016 | 31 mars 2015 | |
Observation |
Establishment of appropriate legal structure and preparation and adoption of suitable corporate charter and reporting arrangements for Erdenes MGL | Valeur | EMGL was established in 2007 | Achieved in 2010 | Appropriate legal structure and preparation and ad |
Date | 28 mars 2014 | 23 mai 2016 | 31 mars 2015 | |
Observation |
Consultation with a range of stakeholders including civil society, community members and the private sector undertaken as part of asocial and environmental strategic assessment process. | Valeur | Limited | Fully Achieved. | SESA Consultation process completed. Working local |
Date | 28 mars 2014 | 23 mai 2016 | 31 mars 2015 | |
Observation |