Org. De Financement | Engagements |
---|---|
IDA Credit | 31.10 |
Non-Government Organization (NGO) of Borrowing Country | 0.20 |
Borrower/Recipient | 1.70 |
P058706
Closed
Christian Peter
N/A
20 avril 2000
(à la date de présentation au Conseil)
26 février 2002
8 juillet 1999
USD 33.00 millions
N/A
2002
USD 31.10 millions
B
15 janvier 2013
31 décembre 2009
BANK APPROVED
Org. De Financement | Engagements |
---|---|
IDA Credit | 31.10 |
Non-Government Organization (NGO) of Borrowing Country | 0.20 |
Borrower/Recipient | 1.70 |
Type de produit/service | BIRD/IDA |
---|---|
Engagement BIRD | N/D |
Engagement IDA | 31.10 |
Engagement BIRD + IDA | 31.10 |
Instrument de prêt | |
---|---|
Élément don | N/D |
Coût total du projet** | 33.00 |
Name | Review | Date |
---|---|---|
Financial Management | Satisfactory | 2010-01-09 |
Counterpart Funding | Satisfactory | 2010-01-09 |
Overall Safeguards Rating | Moderately Satisfactory | 2010-01-09 |
Progress towards achievement of PDO | Moderately Unsatisfactory | 2010-01-09 |
Procurement | Moderately Satisfactory | 2010-01-09 |
Project Management | Moderately Satisfactory | 2010-01-09 |
Monitoring and Evaluation | Moderately Satisfactory | 2010-01-09 |
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2010-01-09 |
INDICATEUR | BILAN DE FIN D’EXÉCUTION ET DE RÉSULTATS: 06-25-2010 |
---|---|
Résultats | Moderately Unsatisfactory |
Risques pour les résultats de développement | Substantial |
Performance de la Banque | Moderately Unsatisfactory |
Performance de l'emprunteur | Moderately Unsatisfactory |
Performance de l’État | Moderately Unsatisfactory |
Organisme d'exécution | Moderately Unsatisfactory |
INDICATEUR | EXAMEN RFE: 06-08-2011 | RAPPORT D’ÉVALUATION RÉTROSPECTIVE DE PROJET: 06-29-2011 |
---|---|---|
Évaluation Des Résultats | Unsatisfactory | Unsatisfactory |
Risques Pour Les Résultats De Développement | High | High |
Performance De La Banque | Moderately Unsatisfactory | Moderately Unsatisfactory |
Performance De L'emprunteur | Moderately Unsatisfactory | Moderately Unsatisfactory |
Performance De L’état | Moderately Unsatisfactory | Moderately Unsatisfactory |
Organisme D'exécution | Moderately Unsatisfactory | Not Rated |
Qualité Des Rfe | Satisfactory | Not Rated |
Qualité Du Suivi-évaluation | Negligible | Negligible |
INDICATEUR | NIVEAU DE RÉFÉRENCE | EN COURS | OBJECTIF |
---|
Area of forests on Tanzania Mainland managed according to approved forest management plans (incl. Community Based Forest management(CBFM) and Joint Forest Managament (JFM)) | Valeur | 3.6 million has | 5.46 million has (1.34 m has publicly owned produc | 4.8 million has |
Date | 30 juin 2006 | 18 novembre 2009 | 31 décembre 2009 | |
Observation | Unchaged since last mission, target overachieved. |
Area of forest plantations under private management agreements (concessions, co-management, or communities designated). | Valeur | 0 | 16,563 hectares | 20,000 has of publicly owned plantation under priv |
Date | 29 juin 2007 | 18 novembre 2009 | 31 décembre 2009 | |
Observation | 3 concession agreements are being developed (MOUs but no contracts have been signed). |
INDICATEUR | NIVEAU DE RÉFÉRENCE | EN COURS | OBJECTIF |
---|
TFS framework documents approved by President's Office-Public Sector Management. TFS establishment order signed, CEO appointed and TFS operational. | Valeur | Legal framework for the establishment of the Tanza | PO-PSM approval for framework document obtained, e | TFS establishment order signed, CEO appointed and |
Date | 15 mai 2002 | 18 novembre 2009 | 31 décembre 2009 | |
Observation |
MNRT/FBD assets evaluated and transferred to TFS. | Valeur | Evaluation report available | Assets evaluated | MNRT/FBD assets transferred to TFS |
Date | 29 juin 2007 | 18 novembre 2009 | 31 décembre 2009 | |
Observation | No change assets awaiting transfer once TFS formally establsihed. |
Number of Local Government or NGO staff trained in PFM facilitation and actively carrying it out. | Valeur | 96 field staff trained | 400 field staff trained, PFM activities well under | Trained field staff actively working in PFM activi |
Date | 29 juin 2007 | 18 novembre 2009 | 31 décembre 2009 | |
Observation | No change since last ISR. |
Revenue collected from forest goods and services. | Valeur | TSh. 15 billion | TSh. 21.8 billion | TSh. 24 billion |
Date | 29 juin 2007 | 18 novembre 2009 | 31 décembre 2009 | |
Observation | FBD expects to achieve the TShs. 24 billion target, this will be contributed to management plans prepared under TFCMP, Improved LawEnforcement through Forest S urveillance Units Facilitated through TFCMP.Improvements of Leakages as advised through TFCMP assignments of TransportBased Fees for Charcoal & Log Tracking S ystemt. |
Revenue Tracking System introduced and decentralized at district level | Valeur | Revenue Tracking System developed | Revenue Tracking System has been introduced and is | Revenue Tracking System operational at district le |
Date | 29 juin 2007 | 18 novembre 2009 | 31 décembre 2009 | |
Observation |
Up-to-date and reliable forest & ecosystem resource data available for Mainland Tanzania | Valeur | National Forest Inventory (NFI) methodology develo | Plantation inventory completed, National Forest Mo | NFI completed for 50% of Mainland Tanzania |
Date | 29 juin 2007 | 18 novembre 2009 | 31 décembre 2009 | |
Observation | Delay of field work is due to a new methodology for NAFORMA which is under development in Collaboration with FAO, to integratemonitoring REDD relevant indicat ors. |
Area of forests set aside and sustainably managed for charcoal production. | Valeur | 2,000 has | 4,500 hectares set aside as an integral part of th | 4,500 has |
Date | 29 juin 2007 | 18 novembre 2009 | 31 décembre 2009 | |
Observation |
Forest management guidelines revised and approved to reflect benefits and costs of multi-stakeholder arrangements in forest plantation management. | Valeur | Guidelines under review | Forest management plan guidelines have been revise | Guidelines operational |
Date | 29 juin 2007 | 18 novembre 2009 | 31 décembre 2008 | |
Observation |
Increase in capital of the Eastern Arc Mountains Conservation Endowment Fund (EAMCEF). | Valeur | US$7.2 million, no additional fundraising initiate | USD7.5 million, bi-lateral agreement between Unile | US$11 million |
Date | 29 juin 2007 | 18 novembre 2009 | 31 décembre 2009 | |
Observation | Sount fund mnagement straegy helped a rebounce to USD7.5 million after a low of USD5.5 million in February 2009. |
Number of grants provided by EAMCEF for biodiversity conservation projects. | Valeur | 20 | 80 | 80 |
Date | 29 juin 2007 | 18 novembre 2009 | 31 octobre 2009 | |
Observation | No change since last ISR. |
Preparation and pilot implementation of management plans of selected critical watershed forests | Valeur | 0 | 50,000 ha pilot management plans of selected criti | 50,000 ha pilot management plans of selected criti |
Date | 29 juin 2007 | 18 novembre 2009 | 31 décembre 2009 | |
Observation | no change since last ISR. |
New transport based fees and market-based forest produce pricing systems introduced and operational | Valeur | Systems not developed | Systems tested, GOT notice for new transport based | System operational in selected regions. |
Date | 29 juin 2007 | 18 novembre 2009 | 31 décembre 2009 | |
Observation |
Forest management plans for production forests updated or revised | Valeur | Forest management plans outdated | 1,338,800 ha of management plans for production fo | 150,000 has of management plans for production for |
Date | 29 juin 2007 | 18 novembre 2009 | 31 décembre 2009 | |
Observation | No change since lasi ISR. |
Mechanisms for forest biodiversity conservation are more fully established (Areas of mountainous forest reserves managed under IUCNcodes) | Valeur | |||
Date | 15 mai 2002 | 18 novembre 2009 | 31 décembre 2009 | |
Observation |