The development objective of the Rural Electrification Hybrid System Project for Mali is to expand access to modern energy services in rural areas of the recipient and to increase renewable energy generation in target areas. There are three components to the project. The first component of the project is service improvement and extension of existing mini-grids. This component will increase renewable energy generation capacity in existing rural power...

* Le résumé de projet étant tiré du document d'évaluation de projet (PAD), du rapport d'évaluation (SAR) ou du document du programme (PGD), il peut ne pas refléter exactement la teneur du projet en son état actuel.

Voir plus

Objectif de développement

The objective of the Project is to expand access to modern energy services in rural areas of the Recipient and to increase renewable energy generation in target areas.

Clé Détails

Projet Détails

  • P131084

  • Closed

  • Abdou Mbaye , Leopold Sedogo, Madina Tall

  • Republic of Mali

  • Mali

  • 27 août 2013

  • (à la date de présentation au Conseil)

    11 décembre 2013

  • 18 juin 2014

  • USD 44.90 millions

  • B

  • N/A

  • 31 mars 2023

  • Yes

  • BANK APPROVED

  • 29 mars 2024

  • Notes

Finances

Plan De Financement (Millions De Dollars)

Pas de données disponibles.
Org. De Financement Engagements
IDA Credit 25.00
Global Partnership on Output-based Aid 5.00
Strategic Climate Fund Grant 14.90

Financement total du projet (USD millions)

Type de produit/service BIRD/IDA
Engagement BIRD N/D
Engagement IDA 25.00
Engagement BIRD + IDA 25.00
Instrument de prêt
Élément don 19.90
Coût total du projet** 44.90

État récapitulatif du financement de la Banque (USD millions) au 31 mars 2025

Télécharger:
Pas de données disponibles.
Org. De Financement Date D'approbation Date De Cloture Montant En Principal Décaissé Remboursements Intérêts, Charges Et Commissions Financières

Activité financière détaillée au 31 mars 2025

Télécharger:
Pas de données disponibles.
Période Org. De Financement Type De Transaction Montant (USD)

Footnotes

Ratings

EXÉCUTION DU PROJET

Name Review Date
Progress towards achievement of PDO Satisfactory 2023-01-27
Project Management Satisfactory 2023-01-27
Financial Management Satisfactory 2023-01-27
Monitoring and Evaluation Satisfactory 2023-01-27
Overall Implementation Progress (IP) Satisfactory 2023-01-27
Overall Safeguards Rating Moderately Satisfactory 2023-01-27
Procurement Moderately Satisfactory 2023-01-27

FIN D’EXÉCUTION DU PROJET

INDICATEURBILAN DE FIN D’EXÉCUTION ET DE RÉSULTATS: 03-29-2024
RésultatsSubstantial
Risques pour les résultats de développement
Performance de la BanqueSubstantial
Performance de l'emprunteur
Performance de l’État
Organisme d'exécution

NOTATION DE L’ÉVALUATION INDÉPENDANTE

INDICATEUREXAMEN RFE: 09-20-2024RAPPORT D’ÉVALUATION RÉTROSPECTIVE DE PROJET:
Évaluation Des RésultatsSatisfactory N/a
Risques Pour Les Résultats De DéveloppementN/a
Performance De La BanqueSatisfactoryN/a
Performance De L'emprunteurN/a
Performance De L’étatN/a
Organisme D'exécutionN/a
Qualité Des RfeSubstantialN/a
Qualité Du Suivi-évaluationSubstantialN/a

Cadre de résultats

INDICATEURS DES OBJECTIFS DE DÉVELOPPEMENT DU PROJET

INDICATEURNIVEAU DE RÉFÉRENCE EN COURS OBJECTIF
  • People provided with access to electricity under the project by household connections - other renewable energy - off gridValeur0.00297947.00550800.00
    Date15 novembre 201331 mars 202330 septembre 2021
    Observation
  • Annual generation of electricity from renewable energies (solar)Valeur0.0010654.0013000.00
    Date15 novembre 201331 mars 202330 septembre 2021
    Observation
  • Direct project beneficiariesValeur0.00893934.001000800.00
    Date15 novembre 201331 mars 202330 septembre 2021
    Observation
  • Generation Capacity of Renewable Energy (other than hydropower) constructedValeur0.007.216.18
    Date15 novembre 201331 mars 202330 septembre 2021
    Observation
  • Female beneficiariesValeur0.000.000.00
    Date15 novembre 201325 mai 2018
    Observation
  • Installed solar powerValeur0.007.216.18
    Date15 novembre 201331 mars 202330 septembre 2021
    Observation
  • Annual greenhouse gas emission reductionsValeur0.0013945.0010678.00
    Date15 novembre 201331 mars 202330 septembre 2021
    Observation

INDICATEURS DE RÉSULTATS INTERMÉDIAIRES

INDICATEURNIVEAU DE RÉFÉRENCE EN COURS OBJECTIF
  • Localities reached by information and communication campaignsValeur0.0050.0050.00
    Date15 novembre 201331 mars 202330 septembre 2021
    Observation
  • Distribution lines constructed under the projectValeur0.00227.00225.00
    Date15 novembre 201331 mars 202330 septembre 2021
    Observation
  • Number of CFLs or LEDs distributedValeur0.0094876.0058700.00
    Date15 novembre 201331 mars 202330 septembre 2021
    Observation
  • Hybrid mini-grid systems installedValeur0.0045.0042.00
    Date15 novembre 201331 mars 202330 septembre 2021
    Observation
  • Number of solar lanterns disseminatedValeur0.00110800.0090000.00
    Date15 novembre 201328 juin 202430 septembre 2021
    Observation
  • Number of persons trained under the projectValeur0.00577.00420.00
    Date15 novembre 201331 mars 202330 septembre 2021
    Observation
  • Number of Solar Home systems installedValeur0.009320.006860.00
    Date15 novembre 201331 mars 202330 septembre 2021
    Observation
  • Solar lanterns distributed in schools and socio-community infrastructures in non-electrified rural areasValeur0.0011000.0010800.00
    Date15 novembre 201331 mars 202330 septembre 2021
    Observation
  • Studies related to rural electrification completedValeur0.009.006.00
    Date15 novembre 201331 mars 202330 septembre 2021
    Observation
  • Additional connections to mini-gridsValeur0.009272.009770.00
    Date15 novembre 201331 mars 202330 septembre 2022
    Observation
  • Number of Energy efficient equipment for social infrastructure distributedValeur0.0058.0050.00
    Date15 novembre 201331 mars 202330 septembre 2021
    Observation
  • Project related grievances registered under the project grievance redress mechanism (GRM) and addressedValeur0.00100.00100.00
    Date30 avril 201931 mars 202330 septembre 2021
    Observation
  • Distribution lines constructed or rehabilitated under the projectValeur0.00227.00225.00
    Date15 novembre 201331 mars 202330 septembre 2021
    Observation